Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,045
matching recommendationsNAICS | 3315 | Foundries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0508 # 02 Y:2017 | 02 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $12,114 | $20,000 | Implemented |
UF0508 # 03 Y:2017 | 03 | 2017 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $11,931 | $12,400 | Implemented |
UF0508 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,193 | $2,737 | Implemented |
UF0508 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,144 | $1,169 | Implemented |
UF0508 # 06 Y:2017 | 06 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,564 | $0 | Implemented |
UF0508 # 07 Y:2017 | 07 | 2017 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $3,384 | $640 | Implemented |
UF0508 # 08 Y:2017 | 08 | 2017 | INSTALL OCCUPANCY SENSORS | $1,548 | $478 | Implemented |
UF0508 # 09 Y:2017 | 09 | 2017 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $3,871 | $700 | Implemented |
UD0968 # 01 Y:2017 | 01 | 2017 | REDUCE EXCESSIVE BOILER BLOWDOWN | $8,230 | $0 | Not Implemented |
UD0968 # 02 Y:2017 | 02 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,800 | $0 | Not Implemented |
UD0968 # 03 Y:2017 | 03 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,341 | $0 | Implemented |
UD0968 # 04 Y:2017 | 04 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,217 | $118 | Implemented |
UD0968 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,870 | $0 | Implemented |
UD0968 # 06 Y:2017 | 06 | 2017 | USE COUNTER-CURRENT RINSING TO REDUCE RINSE WATER VOLUME (GRAVURE) | $87,734 | $2,000 | Not Implemented |
UD0968 # 07 Y:2017 | 07 | 2017 | OPTIMIZE PLANT POWER FACTOR | $61,075 | $28,000 | Not Implemented |
UD0968 # 08 Y:2017 | 08 | 2017 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $909,400 | $750,000 | Not Implemented |
UD0968 # 09 Y:2017 | 09 | 2017 | COVER OPEN TANKS | $234,848 | $564,850 | Not Implemented |
UD0968 # 10 Y:2017 | 10 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $80,368 | $6,000 | Not Implemented |
UD0968 # 11 Y:2017 | 11 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $68,688 | $12,000 | Not Implemented |
UD0968 # 12 Y:2017 | 12 | 2017 | INSULATE BARE EQUIPMENT | $31,081 | $33,760 | Not Implemented |
UD0968 # 13 Y:2017 | 13 | 2017 | USE OPTIMUM TEMPERATURE | $4,293 | $0 | Implemented |
UD0968 # 14 Y:2017 | 14 | 2017 | INSTALL / REPAIR INSULATION ON STEAM LINES | $687 | $1,810 | Not Implemented |
UD0968 # 15 Y:2017 | 15 | 2017 | USE OPTIMUM THICKNESS INSULATION | $162 | $344 | Not Implemented |
UD0968 # 16 Y:2017 | 16 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,850 | $38,175 | Implemented |
UD0968 # 17 Y:2017 | 17 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $27,353 | $42,400 | Implemented |