Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
150
matching recommendationsNAICS | 33151 | Ferrous Metal Foundries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CW0127 # 02 Y:2023 | 02 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $16,199 | $33,933 | n/a |
CW0127 # 01 Y:2023 | 01 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $17,576 | $56,000 | n/a |
CW0127 # 05 Y:2023 | 05 | 2023 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $10,872 | $33,000 | n/a |
CW0127 # 03 Y:2023 | 03 | 2023 | RECYCLE CASTING SAND | $414,227 | $38,394 | n/a |
CW0127 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,943 | $21,648 | n/a |
CW0127 # 06 Y:2023 | 06 | 2023 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $9,906 | $19,900 | n/a |
UD0992 # 05 Y:2018 | 05 | 2018 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $3,174 | $9,900 | Not Implemented |
UD0992 # 02 Y:2018 | 02 | 2018 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $48,158 | $1,000 | Not Implemented |
UD0992 # 04 Y:2018 | 04 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $11,815 | $0 | Not Implemented |
UD0992 # 03 Y:2018 | 03 | 2018 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $30,337 | $32,600 | Not Implemented |
UD0992 # 01 Y:2018 | 01 | 2018 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $14,245 | $700 | Implemented |
UD0968 # 12 Y:2017 | 12 | 2017 | INSULATE BARE EQUIPMENT | $31,081 | $33,760 | Not Implemented |
UD0968 # 06 Y:2017 | 06 | 2017 | USE COUNTER-CURRENT RINSING TO REDUCE RINSE WATER VOLUME (GRAVURE) | $87,734 | $2,000 | Not Implemented |
UD0968 # 09 Y:2017 | 09 | 2017 | COVER OPEN TANKS | $234,848 | $564,850 | Not Implemented |
UD0968 # 08 Y:2017 | 08 | 2017 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $909,400 | $750,000 | Not Implemented |
UD0968 # 07 Y:2017 | 07 | 2017 | OPTIMIZE PLANT POWER FACTOR | $61,075 | $28,000 | Not Implemented |
UD0968 # 11 Y:2017 | 11 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $68,688 | $12,000 | Not Implemented |
UD0968 # 17 Y:2017 | 17 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $27,353 | $42,400 | Implemented |
UD0968 # 02 Y:2017 | 02 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,800 | $0 | Not Implemented |
UD0968 # 01 Y:2017 | 01 | 2017 | REDUCE EXCESSIVE BOILER BLOWDOWN | $8,230 | $0 | Not Implemented |
UD0968 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,870 | $0 | Implemented |
UD0968 # 10 Y:2017 | 10 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $80,368 | $6,000 | Not Implemented |
UD0968 # 13 Y:2017 | 13 | 2017 | USE OPTIMUM TEMPERATURE | $4,293 | $0 | Implemented |
UD0968 # 14 Y:2017 | 14 | 2017 | INSTALL / REPAIR INSULATION ON STEAM LINES | $687 | $1,810 | Not Implemented |
UD0968 # 03 Y:2017 | 03 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,341 | $0 | Implemented |