Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,589
matching recommendationsNAICS | 332 | Fabricated Metal Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2312 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,426 | $1,300 | Implemented |
UC2312 # 03 Y:2023 | 03 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $6,502 | $150 | Implemented |
UC2312 # 04 Y:2023 | 04 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,573 | $75 | Implemented |
UC2312 # 05 Y:2023 | 05 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,710 | $1,062 | Implemented |
UC2312 # 07 Y:2023 | 07 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,620 | $19,500 | Implemented |
UC2312 # 08 Y:2023 | 08 | 2023 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $1,522 | $500 | Implemented |
UC2312 # 11 Y:2023 | 11 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $892 | $2,151 | Implemented |
LS2316 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,894 | $135 | Implemented |
LS2316 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $33,726 | $4,515 | Implemented |
LS2316 # 06 Y:2023 | 06 | 2023 | INSTALL OCCUPANCY SENSORS | $460 | $753 | Implemented |
OR0776 # 01 Y:2023 | 01 | 2023 | OPTIMIZE PLANT POWER FACTOR | $1,131 | $6,802 | Implemented |
AS0560 # 02 Y:2023 | 02 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $51,728 | $659,540 | Implemented |
AS0560 # 03 Y:2023 | 03 | 2023 | UPGRADE OBSOLETE EQUIPMENT | $21,635 | $819,000 | Implemented |
AS0560 # 04 Y:2023 | 04 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $5,025 | $75,360 | Implemented |
AS0560 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,759 | $9,900 | Implemented |
AM0888 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $38,950 | $3,000 | Implemented |
AM0888 # 02 Y:2023 | 02 | 2023 | OPTIMIZE PLANT POWER FACTOR | $7,550 | $13,965 | Implemented |
AM0888 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,310 | $5,795 | Implemented |
AM0888 # 05 Y:2023 | 05 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,440 | $0 | Implemented |
AM0888 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,190 | $1,000 | Implemented |
AM0888 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,100 | $4,040 | Implemented |
AM0888 # 08 Y:2023 | 08 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $895 | $0 | Implemented |
AM0888 # 11 Y:2023 | 11 | 2023 | INSTALL OCCUPANCY SENSORS | $235 | $550 | Implemented |
TT0300 # 02 Y:2023 | 02 | 2023 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $41,095 | $32,000 | Implemented |
TT0300 # 08 Y:2023 | 08 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,614 | $19,910 | Implemented |