Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
300
matching recommendationsNAICS | 332 | Fabricated Metal Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0216 # 11 Y:2005 | 11 | 2005 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $12,630 | $18,780 | Not Implemented |
LL0216 # 12 Y:2005 | 12 | 2005 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,040 | $2,303 | Implemented |
LL0195 # 01 Y:2004 | 01 | 2004 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $29,145 | $4,275 | Not Implemented |
LL0195 # 02 Y:2004 | 02 | 2004 | USE PHOTOCELL CONTROLS | $11,834 | $750 | Implemented |
LL0195 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,732 | $4,280 | Implemented |
LL0195 # 04 Y:2004 | 04 | 2004 | USE PHOTOCELL CONTROLS | $4,294 | $1,320 | Implemented |
LL0195 # 05 Y:2004 | 05 | 2004 | OPTIMIZE PLANT POWER FACTOR | $1,111 | $3,200 | Implemented |
LL0195 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $455 | $350 | Implemented |
LL0195 # 07 Y:2004 | 07 | 2004 | INSTALL OCCUPANCY SENSORS | $225 | $240 | Implemented |
LL0195 # 08 Y:2004 | 08 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,500 | $60 | Implemented |
LL0195 # 09 Y:2004 | 09 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $412 | $226 | Implemented |
LL0186 # 01 Y:2004 | 01 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $29,094 | $4,650 | Implemented |
LL0186 # 02 Y:2004 | 02 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $8,122 | $48 | Not Implemented |
LL0186 # 03 Y:2004 | 03 | 2004 | USE PHOTOCELL CONTROLS | $7,508 | $600 | Not Implemented |
LL0186 # 04 Y:2004 | 04 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,551 | $195 | Implemented |
LL0186 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,104 | $2,080 | Implemented |
LL0186 # 06 Y:2004 | 06 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,748 | $4,250 | Implemented |
LL0186 # 07 Y:2004 | 07 | 2004 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $1,313 | $96 | Not Implemented |
LL0186 # 08 Y:2004 | 08 | 2004 | INSTALL OCCUPANCY SENSORS | $694 | $90 | Not Implemented |
LL0186 # 09 Y:2004 | 09 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $452 | $315 | Implemented |
LL0186 # 10 Y:2004 | 10 | 2004 | COMBINE UTILITY METERS | $2,613 | $720 | Implemented |
LL0186 # 11 Y:2004 | 11 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,500 | $60 | Implemented |
LL0182 # 01 Y:2004 | 01 | 2004 | REPLACE BOILER | $172,411 | $79,000 | Not Implemented |
LL0182 # 02 Y:2004 | 02 | 2004 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $54,044 | $325,479 | Not Implemented |
LL0182 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $49,248 | $33,150 | Implemented |