Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
10,512
matching recommendationsNAICS | 332 | Fabricated Metal Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0293 # 09 Y:2004 | 09 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,889 | $210 | Implemented |
WV0293 # 10 Y:2004 | 10 | 2004 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $1,815 | $3,000 | Not Implemented |
WV0293 # 11 Y:2004 | 11 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,657 | $300 | Implemented |
WV0293 # 12 Y:2004 | 12 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $565 | $1,100 | Not Implemented |
WV0293 # 13 Y:2004 | 13 | 2004 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $38,480 | $1,900 | Not Implemented |
LM0074 # 01 Y:2004 | 01 | 2004 | INSULATE BARE EQUIPMENT | $3,094 | $231 | Implemented |
LM0074 # 02 Y:2004 | 02 | 2004 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $1,288 | $1,000 | Implemented |
LM0074 # 03 Y:2004 | 03 | 2004 | PAY BILLS ON TIME TO AVOID LATE FEES | $392 | $0 | Implemented |
LM0074 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,673 | $125 | Implemented |
LM0074 # 05 Y:2004 | 05 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $3,618 | $4,000 | Implemented |
LM0074 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,439 | $1,740 | Implemented |
LM0074 # 07 Y:2004 | 07 | 2004 | INSTALL SKYLIGHTS | $2,237 | $300 | Not Implemented |
LM0074 # 08 Y:2004 | 08 | 2004 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $21,938 | $6,600 | Implemented |
LM0074 # 09 Y:2004 | 09 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $431 | $0 | Not Implemented |
LM0074 # 10 Y:2004 | 10 | 2004 | MODIFY WORKLOAD | $41,860 | $19,000 | Implemented |
UD0694 # 01 Y:2004 | 01 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $318,395 | $324,700 | Not Implemented |
UD0694 # 02 Y:2004 | 02 | 2004 | AIR CONDITION ONLY SPACE NECESSARY | $295,125 | $0 | Implemented |
UD0694 # 03 Y:2004 | 03 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $117,513 | $80,244 | Not Implemented |
UD0694 # 04 Y:2004 | 04 | 2004 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $57,990 | $114,000 | Not Implemented |
UD0694 # 05 Y:2004 | 05 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $33,763 | $51,348 | Implemented |
UD0694 # 06 Y:2004 | 06 | 2004 | REDUCE VENTILATION AIR | $18,999 | $0 | Implemented |
UD0694 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,530 | $5,780 | Implemented |
UD0694 # 08 Y:2004 | 08 | 2004 | USE CONTINUOUS EQUIPMENT WHICH RETAINS PROCESS HEATING CONVEYORS WITHIN THE HEATED CHAMBER | $4,207 | $3,323 | Not Implemented |
UD0694 # 09 Y:2004 | 09 | 2004 | UPGRADE CONTROLS ON COMPRESSORS | $3,140 | $0 | Not Implemented |
UD0694 # 10 Y:2004 | 10 | 2004 | INSTALL OCCUPANCY SENSORS | $1,427 | $210 | Implemented |