Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

46

matching recommendations
Reset
NAICS 332119 Metal Crown, Closure, and Other Metal Stamping (except Automotive)
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WV0302 # 01 Y:2004 01 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,584 $3,731 Implemented
WV0302 # 09 Y:2004 09 2004 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $2,096 $1,967 Not Implemented
WV0302 # 12 Y:2004 12 2004 CONTRACT A WOOD PALLET RECYCLING COMPANY $28,080 $100 Implemented
WV0302 # 10 Y:2004 10 2004 INSTALL OCCUPANCY SENSORS $921 $1,400 Implemented
WV0302 # 11 Y:2004 11 2004 DEVELOP A REPAIR/REPLACE POLICY $731 $300 Implemented
WV0302 # 02 Y:2004 02 2004 USE DEMAND CONTROLLER OR LOAD SHEDDER $3,141 $0 Implemented
WV0302 # 05 Y:2004 05 2004 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $3,067 $7,050 Not Implemented
WV0302 # 07 Y:2004 07 2004 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $2,889 $80 Implemented
WV0302 # 08 Y:2004 08 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,260 $50 Implemented
WV0302 # 06 Y:2004 06 2004 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,066 $2,200 Implemented
WV0302 # 03 Y:2004 03 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,134 $292 Implemented
WV0302 # 04 Y:2004 04 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,072 $7,735 Implemented
WV0302 # 13 Y:2004 13 2004 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $5,450 $5,000 Implemented
SD0334 # 08 Y:2004 08 2004 REUSE / RECYCLE/ SELL PAPER PRODUCTS $7,320 $6,000 Not Implemented
SD0334 # 09 Y:2004 09 2004 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $4,200 $10,000 Not Implemented
SD0334 # 07 Y:2004 07 2004 USE EVAPORATION TO CONCENTRATE MATERIAL $641 $380 Implemented
SD0334 # 06 Y:2004 06 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,155 $0 Not Implemented
SD0334 # 05 Y:2004 05 2004 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $6,008 $10,250 Not Implemented
SD0334 # 04 Y:2004 04 2004 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $9,714 $2,420 Not Implemented
SD0334 # 03 Y:2004 03 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $12,279 $390 Implemented
SD0334 # 02 Y:2004 02 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,538 $31,523 Implemented
SD0334 # 01 Y:2004 01 2004 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $19,914 $22,746 Implemented
AS0374 # 06 Y:2004 06 2004 INSTALL / REPAIR INSULATION ON STEAM LINES $106 $51 Implemented
AS0374 # 05 Y:2004 05 2004 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,873 $1,872 Not Implemented
AS0374 # 03 Y:2004 03 2004 INSTALL OCCUPANCY SENSORS $4,226 $4,125 Not Implemented