Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
50
matching recommendationsNAICS | 3323 | Architectural and Structural Metals Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0855 # 06 Y:2012 | 06 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,118 | $0 | Implemented |
UD0855 # 05 Y:2012 | 05 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,665 | $1,000 | Implemented |
UD0855 # 04 Y:2012 | 04 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,089 | $0 | Implemented |
UD0855 # 01 Y:2012 | 01 | 2012 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $23,100 | $0 | Implemented |
MI0219 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,275 | $1,660 | Implemented |
MI0219 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,003 | $37,014 | Implemented |
MI0219 # 03 Y:2012 | 03 | 2012 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,535 | $1,800 | Implemented |
MI0219 # 05 Y:2012 | 05 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,739 | $6,080 | Implemented |
MI0219 # 07 Y:2012 | 07 | 2012 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $895 | $2,320 | Implemented |
MI0219 # 08 Y:2012 | 08 | 2012 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $734 | $120 | Implemented |
SD0443 # 02 Y:2012 | 02 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,935 | $2,500 | Implemented |
SD0443 # 09 Y:2012 | 09 | 2012 | INSTALL OCCUPANCY SENSORS | $395 | $989 | Implemented |
SD0443 # 08 Y:2012 | 08 | 2012 | USE PHOTOCELL CONTROLS | $1,660 | $2,700 | Implemented |
SD0443 # 07 Y:2012 | 07 | 2012 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,010 | $2,500 | Implemented |
SD0443 # 06 Y:2012 | 06 | 2012 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,400 | $2,500 | Implemented |
SD0443 # 05 Y:2012 | 05 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,415 | $800 | Implemented |
SD0443 # 04 Y:2012 | 04 | 2012 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $1,443 | $618 | Implemented |
SD0443 # 03 Y:2012 | 03 | 2012 | ADD AREA LIGHTING SWITCHES | $420 | $115 | Implemented |
SD0443 # 01 Y:2012 | 01 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $591 | $100 | Implemented |
UM0399 # 01 Y:2012 | 01 | 2012 | UPGRADE CONTROLS ON COMPRESSORS | $5,760 | $200 | Implemented |
UM0399 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,275 | $1,300 | Implemented |
UM0399 # 03 Y:2012 | 03 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $500 | $1,000 | Implemented |
UM0399 # 04 Y:2012 | 04 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,480 | $3,200 | Implemented |
UM0399 # 05 Y:2012 | 05 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,010 | $15,800 | Implemented |
UM0399 # 06 Y:2012 | 06 | 2012 | REDUCE VENTILATION AIR | $11,000 | $10,000 | Implemented |