Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
86
matching recommendationsNAICS | 33251 | Hardware Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0492 # 05 Y:2014 | 05 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,126 | $3,000 | Implemented |
WV0492 # 06 Y:2014 | 06 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,774 | $8,160 | Implemented |
WV0492 # 08 Y:2014 | 08 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,697 | $338 | Implemented |
WV0492 # 10 Y:2014 | 10 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $557 | $1,916 | Implemented |
WV0492 # 11 Y:2014 | 11 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $482 | $356 | Implemented |
WV0492 # 12 Y:2014 | 12 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $185 | $700 | Implemented |
OK0867 # 11 Y:2013 | 11 | 2013 | INSULATE BARE EQUIPMENT | $15 | $44 | Implemented |
OK0867 # 08 Y:2013 | 08 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $346 | $701 | Implemented |
OK0867 # 06 Y:2013 | 06 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,712 | $500 | Implemented |
OK0867 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,837 | $21,300 | Implemented |
OK0867 # 02 Y:2013 | 02 | 2013 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $1,208 | $3,900 | Implemented |
OK0814 # 03 Y:2011 | 03 | 2011 | INSTALL EQUIPMENT TO MOVE PRODUCT | $1,364,602 | $235,960 | Implemented |
OK0814 # 02 Y:2011 | 02 | 2011 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $189,220 | $20,000 | Implemented |
OK0814 # 04 Y:2011 | 04 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,049 | $15,319 | Implemented |
OK0814 # 01 Y:2011 | 01 | 2011 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $262,832 | $1,710,000 | Implemented |
UM0357 # 05 Y:2009 | 05 | 2009 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,523 | $1,359 | Implemented |
UM0357 # 07 Y:2009 | 07 | 2009 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,875 | $7,500 | Implemented |
UM0357 # 06 Y:2009 | 06 | 2009 | INSTALL OCCUPANCY SENSORS | $1,466 | $4,692 | Implemented |
UM0357 # 04 Y:2009 | 04 | 2009 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $5,524 | $2,591 | Implemented |
UM0357 # 03 Y:2009 | 03 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,053 | $42,818 | Implemented |
UM0357 # 02 Y:2009 | 02 | 2009 | USE RADIANT HEATER FOR SPOT HEATING | $48,733 | $25,000 | Implemented |
UM0357 # 01 Y:2009 | 01 | 2009 | INSTALL STORM WINDOWS AND DOORS | $88,261 | $361,980 | Implemented |
MZ0032 # 01 Y:2008 | 01 | 2008 | INSTALL OCCUPANCY SENSORS | $1,456 | $712 | Implemented |
MZ0032 # 03 Y:2008 | 03 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $703 | $0 | Implemented |
MZ0032 # 04 Y:2008 | 04 | 2008 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $757 | $300 | Implemented |