Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
299
matching recommendationsNAICS | 33291 | Metal Valve Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0348 # 06 Y:2011 | 06 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $366 | $3,220 | Implemented |
LL0348 # 07 Y:2011 | 07 | 2011 | INSULATE BARE EQUIPMENT | $145 | $356 | Implemented |
LL0348 # 08 Y:2011 | 08 | 2011 | INSULATE BARE EQUIPMENT | $35 | $56 | Implemented |
WV0423 # 04 Y:2011 | 04 | 2011 | REPAIR AND ELIMINATE STEAM LEAKS | $1,472 | $626 | Implemented |
WV0423 # 05 Y:2011 | 05 | 2011 | INSTALL TIMERS AND/OR THERMOSTATS | $1,173 | $2,443 | Implemented |
WV0423 # 06 Y:2011 | 06 | 2011 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $1,041 | $1,000 | Implemented |
WV0423 # 07 Y:2011 | 07 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $521 | $89 | Implemented |
WV0423 # 08 Y:2011 | 08 | 2011 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $428 | $183 | Implemented |
WV0423 # 09 Y:2011 | 09 | 2011 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $343 | $177 | Implemented |
WV0423 # 12 Y:2011 | 12 | 2011 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $272 | $139 | Implemented |
TT0063 # 04 Y:2011 | 04 | 2011 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $900 | $1,050 | Implemented |
OK0795 # 04 Y:2010 | 04 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,677 | $1,100 | Implemented |
OK0795 # 07 Y:2010 | 07 | 2010 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $896 | $5,000 | Implemented |
OK0795 # 08 Y:2010 | 08 | 2010 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,751 | $1,680 | Implemented |
AM0566 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $48,230 | $111,190 | Implemented |
AM0566 # 03 Y:2009 | 03 | 2009 | TURN OFF EQUIPMENT WHEN NOT IN USE | $35,170 | $1,300 | Implemented |
AM0566 # 04 Y:2009 | 04 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $32,100 | $3,000 | Implemented |
AM0566 # 05 Y:2009 | 05 | 2009 | USE SYNTHETIC LUBRICANT | $6,890 | $0 | Implemented |
AM0566 # 08 Y:2009 | 08 | 2009 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,950 | $0 | Implemented |
AM0566 # 09 Y:2009 | 09 | 2009 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,780 | $0 | Implemented |
AM0566 # 10 Y:2009 | 10 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,385 | $380 | Implemented |
DL0043 # 02 Y:2009 | 02 | 2009 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,192 | $0 | Implemented |
DL0043 # 03 Y:2009 | 03 | 2009 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $5,472 | $3,500 | Implemented |
DL0043 # 07 Y:2009 | 07 | 2009 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,060 | $0 | Implemented |
IA0429 # 02 Y:2008 | 02 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,875 | $45 | Implemented |