Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
885
matching recommendationsNAICS | 332999 | All Other Miscellaneous Fabricated Metal Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1081 # 07 Y:2024 | 07 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,626 | $7,875 | n/a |
UD1081 # 08 Y:2024 | 08 | 2024 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $3,404 | $0 | n/a |
UD1081 # 01 Y:2024 | 01 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $792 | $0 | n/a |
UD1081 # 02 Y:2024 | 02 | 2024 | REDUCE FLUID FLOW RATES | $29,869 | $3,076 | n/a |
UD1081 # 03 Y:2024 | 03 | 2024 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $55,362 | $6,264 | n/a |
UD1081 # 06 Y:2024 | 06 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $12,481 | $730 | n/a |
UD1081 # 04 Y:2024 | 04 | 2024 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,442 | $0 | n/a |
UD1081 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,187 | $1,235 | n/a |
UD1081 # 09 Y:2024 | 09 | 2024 | OPTIMIZE PLANT POWER FACTOR | $6,380 | $17,600 | n/a |
UD1081 # 10 Y:2024 | 10 | 2024 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $621 | $249 | n/a |
UD1080 # 04 Y:2024 | 04 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $31 | $142 | n/a |
UD1080 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,018 | $952 | n/a |
UD1080 # 02 Y:2024 | 02 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $165 | $0 | n/a |
UD1080 # 01 Y:2024 | 01 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $808 | $0 | n/a |
UD1080 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,541 | $14,110 | n/a |
UD1080 # 03 Y:2024 | 03 | 2024 | LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE | $1,555 | $405 | n/a |
MS0424 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,613 | $19,215 | n/a |
MS0424 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $50,990 | $507,500 | n/a |
MS0424 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $74,358 | $275,000 | n/a |
IC0295 # 06 Y:2024 | 06 | 2024 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $16,247 | $16,893 | n/a |
IC0295 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,221 | $6,343 | n/a |
IC0295 # 02 Y:2024 | 02 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,497 | $558 | n/a |
IC0295 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,690 | $3,413 | n/a |
IC0295 # 07 Y:2024 | 07 | 2024 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $843 | $490 | n/a |
IC0295 # 03 Y:2024 | 03 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $13,248 | $0 | n/a |