Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,737
matching recommendationsNAICS | 333 | Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0467 # 05 Y:2004 | 05 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,000 | $6 | Implemented |
AM0467 # 06 Y:2004 | 06 | 2004 | REUSE RAGS UNTIL COMPLETELY SOILED | $700 | $0 | Implemented |
AM0467 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $420 | $175 | Implemented |
AM0467 # 09 Y:2004 | 09 | 2004 | USE SYNTHETIC LUBRICANT | $240 | $0 | Implemented |
AM0467 # 10 Y:2004 | 10 | 2004 | COMBINE UTILITY METERS | $190 | $0 | Implemented |
LL0188 # 01 Y:2004 | 01 | 2004 | ADD AREA LIGHTING SWITCHES | $37,447 | $4,522 | Implemented |
LL0189 # 01 Y:2004 | 01 | 2004 | OPTIMIZE PLANT POWER FACTOR | $16,554 | $30,485 | Implemented |
LL0189 # 02 Y:2004 | 02 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $14,949 | $8,940 | Implemented |
LL0189 # 06 Y:2004 | 06 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,506 | $42,903 | Implemented |
LL0189 # 08 Y:2004 | 08 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,500 | $60 | Implemented |
LL0189 # 09 Y:2004 | 09 | 2004 | COMBINE UTILITY METERS | $338 | $60 | Implemented |
TA0075 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,473 | $150 | Implemented |
TA0075 # 02 Y:2004 | 02 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $12,900 | $771 | Implemented |
TA0075 # 03 Y:2004 | 03 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,615 | $150 | Implemented |
TA0075 # 05 Y:2004 | 05 | 2004 | INSTALL SET-BACK TIMERS | $2,163 | $2,350 | Implemented |
TA0075 # 06 Y:2004 | 06 | 2004 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $1,300 | $50 | Implemented |
TA0075 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,288 | $0 | Implemented |
TA0075 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,194 | $1,939 | Implemented |
IA0341 # 02 Y:2004 | 02 | 2004 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $2,502 | $700 | Implemented |
IA0341 # 03 Y:2004 | 03 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,519 | $460 | Implemented |
IA0341 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $727 | $105 | Implemented |
IA0341 # 05 Y:2004 | 05 | 2004 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $8,040 | $54,300 | Implemented |
IA0341 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $182 | $194 | Implemented |
IA0341 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $874 | $1,990 | Implemented |
IA0341 # 08 Y:2004 | 08 | 2004 | INSTALL OCCUPANCY SENSORS | $123 | $289 | Implemented |