Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,228
matching recommendationsNAICS | 333 | Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0433 # 06 Y:2011 | 06 | 2011 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $17,685 | $29,025 | Not Implemented |
NC0433 # 07 Y:2011 | 07 | 2011 | DEVELOP A REPAIR/REPLACE POLICY | $2,159 | $3,999 | Implemented |
NC0433 # 08 Y:2011 | 08 | 2011 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $276 | $0 | Not Implemented |
IA0470 # 01 Y:2011 | 01 | 2011 | INSTALL OCCUPANCY SENSORS | $1,446 | $2,556 | Implemented |
IA0470 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,520 | $63,232 | Implemented |
IA0470 # 03 Y:2011 | 03 | 2011 | USE PHOTOCELL CONTROLS | $208 | $210 | Implemented |
IA0470 # 04 Y:2011 | 04 | 2011 | REDUCE VENTILATION AIR | $1,038 | $144 | Implemented |
IA0470 # 05 Y:2011 | 05 | 2011 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,631 | $15,000 | Not Implemented |
OK0815 # 01 Y:2011 | 01 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $57,281 | $13,000 | Not Implemented |
OK0815 # 02 Y:2011 | 02 | 2011 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $12,351 | $0 | Implemented |
OK0815 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,341 | $930 | Implemented |
OK0815 # 04 Y:2011 | 04 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $340 | $950 | Implemented |
OK0815 # 05 Y:2011 | 05 | 2011 | INSTALL OCCUPANCY SENSORS | $2,608 | $2,198 | Not Implemented |
OK0815 # 06 Y:2011 | 06 | 2011 | DISCONNECT BALLASTS | $849 | $696 | Not Implemented |
OK0815 # 07 Y:2011 | 07 | 2011 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $15,876 | $3,096 | Not Implemented |
OK0815 # 08 Y:2011 | 08 | 2011 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,335 | $20,544 | Not Implemented |
OK0815 # 09 Y:2011 | 09 | 2011 | INSULATE BARE EQUIPMENT | $3,531 | $633 | Implemented |
MS0381 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,400 | $293 | Implemented |
MS0381 # 02 Y:2011 | 02 | 2011 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $31,659 | $34,108 | Not Implemented |
MS0381 # 03 Y:2011 | 03 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $264 | $317 | Not Implemented |
MS0381 # 04 Y:2011 | 04 | 2011 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $14,709 | $57,080 | Not Implemented |
MS0381 # 05 Y:2011 | 05 | 2011 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $2,990 | $12,600 | Implemented |
MS0381 # 06 Y:2011 | 06 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,037 | $8,580 | Implemented |
NC0432 # 01 Y:2011 | 01 | 2011 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $14,064 | $24,000 | Not Implemented |
NC0432 # 02 Y:2011 | 02 | 2011 | REPAIR FAULTY LOUVERS AND DAMPERS | $7,824 | $2,500 | Implemented |