Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
212
matching recommendationsNAICS | 333 | Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CC0027 # 08 Y:2023 | 08 | 2023 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $27,290 | $782,250 | n/a |
CC0027 # 07 Y:2023 | 07 | 2023 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $91 | $600 | n/a |
CC0027 # 06 Y:2023 | 06 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $7,831 | $93,870 | n/a |
CC0027 # 05 Y:2023 | 05 | 2023 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $26,412 | $80,000 | n/a |
CC0027 # 04 Y:2023 | 04 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,831 | $10,000 | n/a |
CC0027 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,571 | $25,000 | n/a |
CC0027 # 01 Y:2023 | 01 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,444 | $8,455 | n/a |
CC0027 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $176 | $351 | n/a |
CC0023 # 01 Y:2023 | 01 | 2023 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $55,102 | $47,144 | n/a |
CC0023 # 02 Y:2023 | 02 | 2023 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $12,633 | $40,000 | n/a |
CC0023 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $147,864 | $750,960 | n/a |
CC0021 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,378 | $25,947 | n/a |
CC0021 # 07 Y:2023 | 07 | 2023 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $6,928 | $5,000 | n/a |
CC0021 # 06 Y:2023 | 06 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,760 | $0 | n/a |
CC0021 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,085 | $35,000 | n/a |
CC0021 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,174 | $0 | n/a |
CC0021 # 03 Y:2023 | 03 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,396 | $15,000 | n/a |
CC0021 # 01 Y:2023 | 01 | 2023 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $50,657 | $5,000 | n/a |
NC0652 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $465 | $390 | Implemented |
NC0652 # 04 Y:2020 | 04 | 2020 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $11,865 | $500 | Implemented |
NC0652 # 05 Y:2020 | 05 | 2020 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $40,922 | $1,000 | Not Implemented |
NC0652 # 06 Y:2020 | 06 | 2020 | CONDENSE OPERATION INTO ONE BUILDING | $6,086 | $4,800 | Not Implemented |
NC0652 # 01 Y:2020 | 01 | 2020 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,160 | $100 | Not Implemented |
NC0652 # 02 Y:2020 | 02 | 2020 | INSTALL OCCUPANCY SENSORS | $631 | $700 | Implemented |
NC0653 # 01 Y:2020 | 01 | 2020 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $19,814 | $4,460 | Not Implemented |