Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
35
matching recommendationsNAICS | 3331 | Agriculture, Construction, and Mining Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TA0129 # 03 Y:2006 | 03 | 2006 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $10,615 | $0 | Implemented |
TA0129 # 01 Y:2006 | 01 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,250 | $1,944 | Implemented |
TA0129 # 05 Y:2006 | 05 | 2006 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $48,887 | $0 | Implemented |
TA0123 # 04 Y:2006 | 04 | 2006 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,515 | $340 | Implemented |
TA0123 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,565 | $780 | Implemented |
TA0123 # 02 Y:2006 | 02 | 2006 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $13,420 | $0 | Implemented |
WI0523 # 06 Y:2006 | 06 | 2006 | USE SYNTHETIC LUBRICANT | $1,970 | $0 | Implemented |
WI0523 # 03 Y:2006 | 03 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,347 | $1,000 | Implemented |
IA0391 # 03 Y:2006 | 03 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $136 | $89 | Implemented |
IA0391 # 01 Y:2006 | 01 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,991 | $410 | Implemented |
IA0391 # 04 Y:2006 | 04 | 2006 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $3,433 | $1,735 | Implemented |
IA0391 # 07 Y:2006 | 07 | 2006 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $804 | $600 | Implemented |
UD0741 # 08 Y:2006 | 08 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,097 | $0 | Implemented |
UD0741 # 03 Y:2006 | 03 | 2006 | INSTALL TIMERS AND/OR THERMOSTATS | $18,067 | $110 | Implemented |
UD0741 # 04 Y:2006 | 04 | 2006 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $16,240 | $0 | Implemented |
UD0741 # 05 Y:2006 | 05 | 2006 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $9,135 | $2,800 | Implemented |
UD0741 # 07 Y:2006 | 07 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,802 | $840 | Implemented |
UD0741 # 09 Y:2006 | 09 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,261 | $0 | Implemented |
BD0301 # 05 Y:2006 | 05 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,640 | $500 | Implemented |
BD0301 # 07 Y:2006 | 07 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $763 | $500 | Implemented |
BD0301 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $342 | $350 | Implemented |
BD0301 # 04 Y:2006 | 04 | 2006 | USE PHOTOCELL CONTROLS | $1,759 | $1,750 | Implemented |
BD0301 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,786 | $1,800 | Implemented |
BD0301 # 02 Y:2006 | 02 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $43,599 | $22,780 | Implemented |
BD0301 # 01 Y:2006 | 01 | 2006 | USE RADIANT HEATER FOR SPOT HEATING | $94,570 | $91,000 | Implemented |