IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

117

matching recommendations
Reset
NAICS 3331 Agriculture, Construction, and Mining Machinery Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AS0384 # 09 Y:2004 09 2004 INSULATE BARE EQUIPMENT $902 $251 Implemented
AS0384 # 08 Y:2004 08 2004 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $904 $961 Not Implemented
AS0384 # 07 Y:2004 07 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,575 $20 Implemented
AS0384 # 06 Y:2004 06 2004 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,696 $3,600 Not Implemented
AS0384 # 05 Y:2004 05 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $15,859 $180 Implemented
AS0384 # 04 Y:2004 04 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,206 $88,805 Not Implemented
AS0384 # 03 Y:2004 03 2004 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $26,000 $22,316 Implemented
AS0384 # 02 Y:2004 02 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $34,877 $495 Not Implemented
AS0384 # 01 Y:2004 01 2004 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $58,500 $1,130 Not Implemented
LL0197 # 07 Y:2004 07 2004 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $1,500 $30 Implemented
LL0197 # 05 Y:2004 05 2004 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN $745 $152 Implemented
LL0197 # 03 Y:2004 03 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,042 $2,920 Implemented
LL0197 # 01 Y:2004 01 2004 TURN OFF EQUIPMENT WHEN NOT IN USE $19,102 $30 Implemented
OK0678 # 09 Y:2004 09 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $546 $1,154 Implemented
LL0197 # 04 Y:2004 04 2004 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,020 $990 Implemented
OK0678 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,075 $823 Implemented
LL0197 # 06 Y:2004 06 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $323 $245 Implemented
OK0678 # 05 Y:2004 05 2004 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $22,602 $28,350 Not Implemented
LL0197 # 02 Y:2004 02 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,439 $30 Not Implemented
OK0678 # 08 Y:2004 08 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,847 $14,078 Not Implemented
OK0678 # 06 Y:2004 06 2004 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $5,188 $12,597 Not Implemented
OK0678 # 03 Y:2004 03 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,836 $10,835 Implemented
OK0678 # 04 Y:2004 04 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $13,162 $800 Implemented
OK0678 # 07 Y:2004 07 2004 INSTALL SET-BACK TIMERS $3,347 $2,200 Implemented
OK0678 # 02 Y:2004 02 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,817 $3,690 Implemented