IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

248

matching recommendations
Reset
NAICS 333413 Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TA0117 # 06 Y:2006 06 2006 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $45,290 $22,980 Not Implemented
TA0110 # 01 Y:2005 01 2005 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $11,425 $0 Not Implemented
TA0110 # 02 Y:2005 02 2005 OPTIMIZE PLANT POWER FACTOR $6,850 $13,700 Not Implemented
TA0110 # 03 Y:2005 03 2005 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $3,925 $0 Not Implemented
TA0110 # 04 Y:2005 04 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,880 $1,080 Not Implemented
TA0110 # 05 Y:2005 05 2005 USE EVAPORATION TO CONCENTRATE MATERIAL $4,083 $5,319 Not Implemented
TA0110 # 06 Y:2005 06 2005 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $1,362 $0 Not Implemented
TA0110 # 07 Y:2005 07 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $969 $262 Not Implemented
UD0674 # 01 Y:2003 01 2003 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $18,633 $45,760 Not Implemented
UD0674 # 02 Y:2003 02 2003 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $8,166 $30,000 Implemented
UD0674 # 03 Y:2003 03 2003 MODIFY STARTUP/SHUTDOWN TIMES $2,311 $0 Not Implemented
UD0674 # 04 Y:2003 04 2003 INSULATE BARE EQUIPMENT $1,353 $2,168 Not Implemented
UD0674 # 05 Y:2003 05 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,100 $3,078 Not Implemented
UD0674 # 06 Y:2003 06 2003 INSTALL TIMERS AND/OR THERMOSTATS $753 $1,048 Not Implemented
UD0674 # 07 Y:2003 07 2003 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $715 $0 Implemented
UD0674 # 08 Y:2003 08 2003 ADD AREA LIGHTING SWITCHES $687 $500 Not Implemented
UD0674 # 09 Y:2003 09 2003 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) $623 $604 Not Implemented
UD0674 # 10 Y:2003 10 2003 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $554 $2,200 Implemented
UD0674 # 11 Y:2003 11 2003 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $509 $142 Not Implemented
UD0674 # 12 Y:2003 12 2003 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $481 $0 Implemented
UD0674 # 13 Y:2003 13 2003 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $475 $350 Not Implemented
UD0674 # 14 Y:2003 14 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $360 $100 Implemented
UD0674 # 15 Y:2003 15 2003 DISCONNECT BALLASTS $313 $44 Implemented