Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
37
matching recommendationsNAICS | 333413 | Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0647 # 05 Y:2020 | 05 | 2020 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $124,057 | $600,000 | Not Implemented |
NC0647 # 04 Y:2020 | 04 | 2020 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $20,880 | $5,000 | Not Implemented |
NC0647 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $192 | $135 | Not Implemented |
NC0647 # 02 Y:2020 | 02 | 2020 | INSTALL OCCUPANCY SENSORS | $2,488 | $5,708 | Not Implemented |
NC0647 # 01 Y:2020 | 01 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,099 | $20,000 | Not Implemented |
NC0530 # 02 Y:2014 | 02 | 2014 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $1,055 | $0 | Implemented |
NC0530 # 01 Y:2014 | 01 | 2014 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $14,069 | $54,000 | Not Implemented |
NC0530 # 03 Y:2014 | 03 | 2014 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,962 | $200 | Implemented |
NC0530 # 04 Y:2014 | 04 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,946 | $18,000 | Not Implemented |
NC0530 # 05 Y:2014 | 05 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,542 | $5,000 | Not Implemented |
NC0530 # 06 Y:2014 | 06 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $443 | $200 | Implemented |
NC0530 # 07 Y:2014 | 07 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,767 | $4,000 | Not Implemented |
NC0530 # 08 Y:2014 | 08 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,623 | $2,350 | Implemented |
NC0530 # 09 Y:2014 | 09 | 2014 | INSTALL OCCUPANCY SENSORS | $2,127 | $6,420 | Not Implemented |
NC0530 # 10 Y:2014 | 10 | 2014 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $686 | $563 | Implemented |
NC0530 # 11 Y:2014 | 11 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $632 | $176 | Implemented |
NC0530 # 12 Y:2014 | 12 | 2014 | USE PHOTOCELL CONTROLS | $341 | $80 | Not Implemented |
NC0530 # 13 Y:2014 | 13 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $763 | $2,400 | Not Implemented |
NC0530 # 14 Y:2014 | 14 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $2,001 | $4,256 | Implemented |
NC0497 # 09 Y:2013 | 09 | 2013 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $360 | $650 | Implemented |
NC0497 # 01 Y:2013 | 01 | 2013 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $15,740 | $70,400 | Implemented |
NC0497 # 02 Y:2013 | 02 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,761 | $100 | Implemented |
NC0497 # 03 Y:2013 | 03 | 2013 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,793 | $2,250 | Not Implemented |
NC0497 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,827 | $11,647 | Implemented |
NC0497 # 05 Y:2013 | 05 | 2013 | INSTALL OCCUPANCY SENSORS | $13,386 | $2,785 | Implemented |