IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

273

matching recommendations
Reset
NAICS 333517 Machine Tool Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0982 # 08 Y:2018 08 2018 COVER OPEN TANKS $700 $460 Not Implemented
UD0982 # 13 Y:2018 13 2018 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $13,372 $10,000 Implemented
UD0982 # 01 Y:2018 01 2018 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $21,886 $0 Implemented
UD0982 # 06 Y:2018 06 2018 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $2,208 $3,500 Implemented
UD0982 # 09 Y:2018 09 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $46,311 $113,386 Not Implemented
UD0982 # 11 Y:2018 11 2018 INSTALL OCCUPANCY SENSORS $5,167 $1,500 Implemented
UD0982 # 07 Y:2018 07 2018 COVER OPEN TANKS $268 $0 Not Implemented
UD0982 # 03 Y:2018 03 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,010 $500 Implemented
UD0982 # 04 Y:2018 04 2018 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $9,415 $0 Implemented
UD0982 # 02 Y:2018 02 2018 REDUCE VENTILATION AIR $9,420 $3,000 Implemented
UD0982 # 05 Y:2018 05 2018 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $6,501 $8,000 Implemented
UD0982 # 12 Y:2018 12 2018 ADD AREA LIGHTING SWITCHES $675 $500 Implemented
IC0199 # 04 Y:2017 04 2017 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,064 $50 Not Implemented
IC0199 # 05 Y:2017 05 2017 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,586 $4,651 Not Implemented
IC0199 # 02 Y:2017 02 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,101 $1,146 Not Implemented
IC0199 # 01 Y:2017 01 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $17,264 $4,650 Not Implemented
IC0199 # 03 Y:2017 03 2017 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $7,964 $3,000 Not Implemented
UD0960 # 10 Y:2017 10 2017 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $2,121 $0 Not Implemented
UD0960 # 11 Y:2017 11 2017 USE MINIMUM STEAM OPERATING PRESSURE $826 $0 Not Implemented
UD0960 # 07 Y:2017 07 2017 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $8,266 $3,000 Not Implemented
UD0960 # 06 Y:2017 06 2017 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $514 $1,425 Implemented
UD0960 # 09 Y:2017 09 2017 REDUCE EXCESSIVE BOILER BLOWDOWN $5,234 $7,500 Not Implemented
UD0960 # 08 Y:2017 08 2017 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS $11,351 $10,000 Not Implemented
UD0960 # 14 Y:2017 14 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,599 $9,362 Not Implemented
UD0960 # 13 Y:2017 13 2017 INSTALL OCCUPANCY SENSORS $6,486 $9,108 Not Implemented