matching recommendationsNAICS | 3336 | Engine, Turbine, and Power Transmission Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0094 # 02 Y:2012 | 02 | 2012 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,797 | $12,000 | Not Implemented |
DL0094 # 03 Y:2012 | 03 | 2012 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $4,058 | $1,450 | Not Implemented |
DL0094 # 04 Y:2012 | 04 | 2012 | AIR CONDITION ONLY SPACE NECESSARY | $780 | $0 | Implemented |
DL0094 # 05 Y:2012 | 05 | 2012 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $384 | $0 | Not Implemented |
DL0094 # 06 Y:2012 | 06 | 2012 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,392 | $7,320 | Not Implemented |
DL0094 # 07 Y:2012 | 07 | 2012 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $570 | $10 | Not Implemented |
MZ0097 # 01 Y:2012 | 01 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $230,479 | $107,601 | Not Implemented |
MZ0097 # 02 Y:2012 | 02 | 2012 | INSULATE BARE EQUIPMENT | $106,168 | $10,690 | Not Implemented |
MZ0097 # 03 Y:2012 | 03 | 2012 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $60,715 | $105,000 | Not Implemented |
MZ0097 # 04 Y:2012 | 04 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $49,961 | $5,000 | Not Implemented |
MZ0097 # 05 Y:2012 | 05 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $29,305 | $35,000 | Implemented |
MZ0097 # 06 Y:2012 | 06 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,968 | $450 | Implemented |
MZ0097 # 07 Y:2012 | 07 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,420 | $2,000 | Not Implemented |
OK0816 # 01 Y:2011 | 01 | 2011 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $20,409 | $71,773 | Not Implemented |
OK0816 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $245 | $1,488 | Implemented |
OK0816 # 03 Y:2011 | 03 | 2011 | INSTALL OCCUPANCY SENSORS | $391 | $456 | Implemented |
OK0816 # 04 Y:2011 | 04 | 2011 | DISCONNECT BALLASTS | $481 | $921 | Not Implemented |
OK0816 # 05 Y:2011 | 05 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $17,462 | $0 | Not Implemented |
OK0816 # 06 Y:2011 | 06 | 2011 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $13,197 | $9,150 | Not Implemented |
OK0816 # 07 Y:2011 | 07 | 2011 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $17,005 | $315,900 | Not Implemented |
OK0816 # 08 Y:2011 | 08 | 2011 | REPLACE BOILER | $26,135 | $24,220 | Implemented |
OK0816 # 09 Y:2011 | 09 | 2011 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,244 | $11,700 | Not Implemented |
OK0816 # 10 Y:2011 | 10 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,037 | $0 | Implemented |
OK0816 # 11 Y:2011 | 11 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,760 | $1,338 | Implemented |
OK0816 # 12 Y:2011 | 12 | 2011 | INSULATE BARE EQUIPMENT | $1,893 | $2,263 | Not Implemented |