Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
38
matching recommendationsNAICS | 333613 | Mechanical Power Transmission Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0616 # 06 Y:2007 | 06 | 2007 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $709 | $300 | Not Implemented |
MA0616 # 05 Y:2007 | 05 | 2007 | INSTALL TIMERS AND/OR THERMOSTATS | $16,346 | $1,088 | Not Implemented |
MA0616 # 04 Y:2007 | 04 | 2007 | RECOVER WASTE HEAT FROM EQUIPMENT | $37,450 | $12,998 | Not Implemented |
MA0616 # 03 Y:2007 | 03 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,603 | $2,550 | Implemented |
MA0616 # 02 Y:2007 | 02 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,128 | $3,725 | Not Implemented |
MA0616 # 01 Y:2007 | 01 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,636 | $132,834 | Not Implemented |
TT0001 # 06 Y:2007 | 06 | 2007 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $1,850 | $3,000 | Implemented |
TT0001 # 04 Y:2007 | 04 | 2007 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $41,993 | $0 | Not Implemented |
TT0001 # 05 Y:2007 | 05 | 2007 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $9,800 | $0 | Not Implemented |
TT0001 # 14 Y:2007 | 14 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $110 | $0 | Not Implemented |
TT0001 # 07 Y:2007 | 07 | 2007 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $1,360 | $1,500 | Implemented |
TT0001 # 08 Y:2007 | 08 | 2007 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,770 | $0 | Not Implemented |
TT0001 # 09 Y:2007 | 09 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,290 | $1,000 | Implemented |
TT0001 # 10 Y:2007 | 10 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $29,038 | $0 | Not Implemented |
TT0001 # 11 Y:2007 | 11 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $45,200 | $0 | Not Implemented |
TT0001 # 12 Y:2007 | 12 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,715 | $11,979 | Implemented |
TT0001 # 13 Y:2007 | 13 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $698 | $600 | Implemented |
TT0001 # 03 Y:2007 | 03 | 2007 | INSTALL TIMERS AND/OR THERMOSTATS | $1,270 | $0 | Not Implemented |
TT0001 # 02 Y:2007 | 02 | 2007 | CLEAN CONDENSER TUBES | $1 | $26,405 | Implemented |
TT0001 # 01 Y:2007 | 01 | 2007 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $2,856 | $3,500 | Implemented |
UD0757 # 01 Y:2007 | 01 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $32,124 | $0 | Implemented |
UD0757 # 02 Y:2007 | 02 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,618 | $48,190 | Not Implemented |
UD0757 # 03 Y:2007 | 03 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,547 | $1,600 | Implemented |
UD0757 # 04 Y:2007 | 04 | 2007 | USE OPTIMUM TEMPERATURE | $8,681 | $0 | Not Implemented |
UD0757 # 05 Y:2007 | 05 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,031 | $0 | Implemented |