IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,619

matching recommendations
Reset
NAICS 3339 Other General Purpose Machinery Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IA0373 # 03 Y:2005 03 2005 COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER $1,412 $143 Implemented
IA0373 # 04 Y:2005 04 2005 RECOVER WASTE HEAT FROM EQUIPMENT $1,473 $1,147 Implemented
IA0373 # 05 Y:2005 05 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,419 $5,844 Implemented
IA0373 # 06 Y:2005 06 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,460 $12,810 Implemented
IA0373 # 07 Y:2005 07 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,784 $2,706 Implemented
IA0373 # 08 Y:2005 08 2005 INSTALL OCCUPANCY SENSORS $1,668 $1,925 Not Implemented
IA0373 # 09 Y:2005 09 2005 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $9,792 $6,208 Implemented
IA0372 # 01 Y:2005 01 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $496 $619 Implemented
IA0372 # 02 Y:2005 02 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $381 $510 Implemented
IA0372 # 03 Y:2005 03 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,734 $5,978 Implemented
IA0372 # 04 Y:2005 04 2005 INSTALL OCCUPANCY SENSORS $519 $462 Implemented
IA0372 # 05 Y:2005 05 2005 AIR CONDITION ONLY SPACE NECESSARY $45,000 $75,000 Implemented
IA0372 # 06 Y:2005 06 2005 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $1,091 $3,517 Not Implemented
OK0715 # 01 Y:2005 01 2005 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $3,938 $3,936 Not Implemented
OK0715 # 02 Y:2005 02 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,111 $918 Not Implemented
OK0715 # 03 Y:2005 03 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,522 $5,175 Not Implemented
OK0715 # 04 Y:2005 04 2005 SCHEDULE BAKING TIMES OF SMALL AND LARGE COMPONENTS $804 $1,825 Not Implemented
OK0715 # 05 Y:2005 05 2005 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $7,665 $47,100 Not Implemented
OK0715 # 06 Y:2005 06 2005 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $1,022 $608 Not Implemented
OK0715 # 07 Y:2005 07 2005 UTILIZE A LESS EXPENSIVE COOLING METHOD $472 $1,000 Not Implemented
OK0715 # 08 Y:2005 08 2005 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $5,361 $26,590 Not Implemented
OK0715 # 09 Y:2005 09 2005 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $20,968 $0 Not Implemented
OK0714 # 01 Y:2005 01 2005 USE POWER DURING OFF-PEAK PERIODS $1,866 $0 Not Implemented
OK0714 # 02 Y:2005 02 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $56,721 $117,780 Implemented
OK0714 # 03 Y:2005 03 2005 USE COMPRESSOR AIR FILTERS $4,058 $920 Implemented