Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
505
matching recommendationsNAICS | 33392 | Material Handling Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0593 # 01 Y:2025 | 01 | 2025 | INSTALL TIMERS AND/OR THERMOSTATS | $19,297 | $0 | n/a |
LE0593 # 03 Y:2025 | 03 | 2025 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $15,667 | $20,000 | n/a |
LE0593 # 04 Y:2025 | 04 | 2025 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,704 | $4,000 | n/a |
LE0593 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,196 | $1,640 | n/a |
LE0593 # 08 Y:2025 | 08 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $727 | $3,014 | n/a |
LE0593 # 05 Y:2025 | 05 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,724 | $13,069 | n/a |
LE0593 # 07 Y:2025 | 07 | 2025 | INSTALL OCCUPANCY SENSORS | $133 | $479 | n/a |
LE0593 # 06 Y:2025 | 06 | 2025 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $7,077 | $35,157 | n/a |
GT0982 # 07 Y:2024 | 07 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $67,468 | $877,960 | n/a |
GT0982 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,510 | $1,850 | n/a |
GT0982 # 02 Y:2024 | 02 | 2024 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,144 | $1,200 | n/a |
GT0982 # 03 Y:2024 | 03 | 2024 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $194 | $135 | n/a |
GT0982 # 05 Y:2024 | 05 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $923 | $800 | n/a |
GT0982 # 06 Y:2024 | 06 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $5,851 | $12,950 | n/a |
GT0982 # 04 Y:2024 | 04 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,571 | $1,100 | n/a |
OK1118 # 07 Y:2024 | 07 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $4,952 | $9,900 | n/a |
OK1118 # 06 Y:2024 | 06 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,488 | $25,000 | n/a |
OK1118 # 05 Y:2024 | 05 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $11,355 | $382,780 | n/a |
OK1118 # 04 Y:2024 | 04 | 2024 | OPTIMIZE PLANT POWER FACTOR | $816 | $4,683 | n/a |
OK1118 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $20,756 | $102,600 | n/a |
OK1118 # 02 Y:2024 | 02 | 2024 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $772 | $450 | n/a |
OK1118 # 03 Y:2024 | 03 | 2024 | COMBINE UTILITY METERS | $453 | $2,200 | n/a |
UD1084 # 01 Y:2024 | 01 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,386 | $0 | Implemented |
UD1084 # 03 Y:2024 | 03 | 2024 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,871 | $6,080 | Not Implemented |
UD1084 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,258 | $1,235 | Not Implemented |