Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,963
matching recommendationsNAICS | 334 | Computer and Electronic Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0210 # 02 Y:2005 | 02 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,088 | $750 | Implemented |
LE0210 # 03 Y:2005 | 03 | 2005 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,616 | $2,000 | Implemented |
LE0210 # 04 Y:2005 | 04 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,330 | $4,866 | Implemented |
LE0210 # 05 Y:2005 | 05 | 2005 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $366 | $140 | Not Implemented |
LE0210 # 06 Y:2005 | 06 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $255 | $80 | Implemented |
LE0210 # 07 Y:2005 | 07 | 2005 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $147 | $360 | Not Implemented |
UF0358 # 01 Y:2005 | 01 | 2005 | INSTALL OCCUPANCY SENSORS | $456 | $503 | Not Implemented |
UF0358 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,300 | $475 | Implemented |
UF0358 # 03 Y:2005 | 03 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,147 | $0 | Implemented |
UF0358 # 04 Y:2005 | 04 | 2005 | USE COMPRESSOR AIR FILTERS | $2,203 | $630 | Implemented |
UF0358 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,181 | $10,652 | Implemented |
UF0358 # 06 Y:2005 | 06 | 2005 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $1,690 | $4,100 | Not Implemented |
UF0358 # 07 Y:2005 | 07 | 2005 | REDUCE HEAT GAIN BY WINDOW TINTING | $1,109 | $2,268 | Implemented |
UF0358 # 08 Y:2005 | 08 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,854 | $1,935 | Not Implemented |
UF0358 # 09 Y:2005 | 09 | 2005 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $4,719 | $8,000 | Implemented |
UF0358 # 10 Y:2005 | 10 | 2005 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $1,430 | $4,800 | Not Implemented |
UF0358 # 11 Y:2005 | 11 | 2005 | PAY UTILITY BILLS ON TIME | $856 | $0 | Implemented |
AS0396 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,749 | $1,000 | Not Implemented |
AS0396 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,877 | $5,000 | Not Implemented |
AS0396 # 03 Y:2005 | 03 | 2005 | REPAIR OR REPLACE STEAM TRAPS | $107 | $50 | Not Implemented |
AS0396 # 04 Y:2005 | 04 | 2005 | INSTALL OCCUPANCY SENSORS | $474 | $150 | Not Implemented |
AS0396 # 05 Y:2005 | 05 | 2005 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $912 | $1,000 | Not Implemented |
AS0396 # 06 Y:2005 | 06 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,302 | $1,000 | Not Implemented |
AS0396 # 07 Y:2005 | 07 | 2005 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $8,063 | $3,000 | Not Implemented |
UD0713 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $84,867 | $94,373 | Not Implemented |