IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

19

matching recommendations
Reset
NAICS 334418 Printed Circuit Assembly (Electronic Assembly) Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SU0317 # 06 Y:2012 06 2012 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $228 $536 Not Implemented
SU0317 # 05 Y:2012 05 2012 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $12,834 $27,300 Implemented
SU0317 # 04 Y:2012 04 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,153 $2,179 Implemented
SU0317 # 03 Y:2012 03 2012 REDUCE VENTILATION AIR $9,899 $14,092 Implemented
SU0317 # 02 Y:2012 02 2012 PREHEAT COMBUSTION AIR WITH WASTE HEAT $1,105 $270 Not Implemented
SU0317 # 01 Y:2012 01 2012 CONDENSE OPERATION INTO ONE BUILDING $333,000 $6,675 Implemented
SU0212 # 10 Y:2005 10 2005 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $148 $527 Implemented
SU0212 # 13 Y:2005 13 2005 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $21,189 $111,859 Not Implemented
SU0212 # 12 Y:2005 12 2005 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $97,661 $114,600 Not Implemented
SU0212 # 11 Y:2005 11 2005 REDUCE VENTILATION AIR $3,820 $13,919 Not Implemented
SU0212 # 01 Y:2005 01 2005 $395 $0 Implemented
SU0212 # 09 Y:2005 09 2005 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $230 $383 Not Implemented
SU0212 # 08 Y:2005 08 2005 INSTALL OCCUPANCY SENSORS $1,966 $2,792 Implemented
SU0212 # 07 Y:2005 07 2005 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $12,179 $10,575 Not Implemented
SU0212 # 06 Y:2005 06 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,637 $1,889 Implemented
SU0212 # 05 Y:2005 05 2005 INSTALL TURBULATORS $985 $571 Not Implemented
SU0212 # 04 Y:2005 04 2005 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $670 $0 Not Implemented
SU0212 # 03 Y:2005 03 2005 USE SYNTHETIC LUBRICANT $375 $0 Implemented
SU0212 # 02 Y:2005 02 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,679 $0 Implemented