Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
37
matching recommendationsNAICS | 334419 | Other Electronic Component Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0434 # 08 Y:2023 | 08 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,530 | $960 | Implemented |
MI0434 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,323 | $7,394 | Implemented |
MI0434 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,225 | $2,000 | Implemented |
MI0434 # 03 Y:2023 | 03 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $14,048 | $0 | Implemented |
MI0434 # 01 Y:2023 | 01 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $29,836 | $550 | Implemented |
MI0413 # 09 Y:2022 | 09 | 2022 | INSTALL OCCUPANCY SENSORS | $355 | $140 | Implemented |
MI0413 # 08 Y:2022 | 08 | 2022 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $755 | $645 | Implemented |
MI0413 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,004 | $1,980 | Implemented |
MI0413 # 02 Y:2022 | 02 | 2022 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,023 | $0 | Implemented |
MI0413 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,013 | $5,249 | Implemented |
MI0413 # 04 Y:2022 | 04 | 2022 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,034 | $580 | Implemented |
MI0413 # 05 Y:2022 | 05 | 2022 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $1,089 | $5,264 | Implemented |
MI0245 # 03 Y:2013 | 03 | 2013 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $24,698 | $160 | Implemented |
MI0245 # 11 Y:2013 | 11 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,631 | $3,190 | Implemented |
MI0245 # 08 Y:2013 | 08 | 2013 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,960 | $7,502 | Implemented |
MI0245 # 07 Y:2013 | 07 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,337 | $80 | Implemented |
MI0245 # 06 Y:2013 | 06 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,737 | $1,660 | Implemented |
MI0245 # 05 Y:2013 | 05 | 2013 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $12,407 | $1,680 | Implemented |
MI0245 # 04 Y:2013 | 04 | 2013 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $13,325 | $13,200 | Implemented |
MI0245 # 01 Y:2013 | 01 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $30,611 | $1,800 | Implemented |
MI0245 # 12 Y:2013 | 12 | 2013 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,214 | $1,694 | Implemented |
UF0428 # 09 Y:2009 | 09 | 2009 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $25,086 | $0 | Implemented |
UF0428 # 07 Y:2009 | 07 | 2009 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $4,285 | $0 | Implemented |
UF0428 # 05 Y:2009 | 05 | 2009 | INSTALL OCCUPANCY SENSORS | $872 | $1,971 | Implemented |
UF0428 # 03 Y:2009 | 03 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,980 | $5,895 | Implemented |