Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
111
matching recommendationsNAICS | 334513 | Instruments and Related Products Manufacturing for Measuring, Displaying, and Controlling Industrial |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL2312 # 01 Y:2023 | 01 | 2023 | INSTALL SPECTRAL REFLECTORS / DELAMP | $5,925 | $0 | Implemented |
UL2312 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $450 | $0 | Implemented |
UL2312 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $5,419 | $15,000 | Implemented |
UL2312 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,248 | $1,620 | Implemented |
DL0206 # 04 Y:2022 | 04 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $14,028 | $27,352 | Implemented |
DL0206 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,447 | $8,852 | Implemented |
DL0206 # 03 Y:2022 | 03 | 2022 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,292 | $0 | Implemented |
DL0206 # 01 Y:2022 | 01 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $917 | $0 | Implemented |
OK1066 # 05 Y:2022 | 05 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,555 | $0 | Implemented |
OK1066 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,177 | $23,400 | Implemented |
WV0604 # 09 Y:2021 | 09 | 2021 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,302 | $4,100 | Implemented |
WV0604 # 05 Y:2021 | 05 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,431 | $403 | Implemented |
WV0604 # 02 Y:2021 | 02 | 2021 | INSTALL OCCUPANCY SENSORS | $20,602 | $23,284 | Implemented |
WV0604 # 04 Y:2021 | 04 | 2021 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $4,330 | $1,500 | Implemented |
WV0604 # 06 Y:2021 | 06 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,500 | $1,792 | Implemented |
WV0604 # 10 Y:2021 | 10 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $733 | $35 | Implemented |
WV0604 # 07 Y:2021 | 07 | 2021 | DEVELOP A REPAIR/REPLACE POLICY | $1,749 | $672 | Implemented |
WV0604 # 03 Y:2021 | 03 | 2021 | INSULATE BARE EQUIPMENT | $18,040 | $7,122 | Implemented |
CO0739 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $291 | $185 | Implemented |
CO0739 # 06 Y:2020 | 06 | 2020 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $11,090 | $0 | Implemented |
CO0739 # 04 Y:2020 | 04 | 2020 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,067 | $0 | Implemented |
OK0868 # 04 Y:2013 | 04 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,792 | $1,851 | Implemented |
OK0868 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,347 | $750 | Implemented |
OK0868 # 06 Y:2013 | 06 | 2013 | INSTALL SET-BACK TIMERS | $3,871 | $606 | Implemented |
OK0868 # 09 Y:2013 | 09 | 2013 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $287 | $456 | Implemented |