Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,095
matching recommendationsNAICS | 335 | Electrical Equipment, Appliance, and Component Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0400 # 05 Y:2010 | 05 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $75 | $200 | Implemented |
AM0571 # 01 Y:2010 | 01 | 2010 | OPTIMIZE PLANT POWER FACTOR | $34,630 | $98,400 | Not Implemented |
AM0571 # 02 Y:2010 | 02 | 2010 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $33,740 | $2,160 | Not Implemented |
AM0571 # 03 Y:2010 | 03 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $24,200 | $300 | Implemented |
AM0571 # 04 Y:2010 | 04 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $10,010 | $31,300 | Implemented |
AM0571 # 05 Y:2010 | 05 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,400 | $1,500 | Implemented |
AM0571 # 06 Y:2010 | 06 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,700 | $1,900 | Implemented |
AM0571 # 07 Y:2010 | 07 | 2010 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $5,605 | $0 | Implemented |
AM0571 # 08 Y:2010 | 08 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,000 | $1,500 | Implemented |
LE0292 # 01 Y:2009 | 01 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $29,667 | $27,000 | Implemented |
LE0292 # 02 Y:2009 | 02 | 2009 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $11,701 | $2,700 | Not Implemented |
LE0292 # 03 Y:2009 | 03 | 2009 | INSTALL TIMERS AND/OR THERMOSTATS | $5,415 | $180 | Implemented |
LE0292 # 04 Y:2009 | 04 | 2009 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,921 | $3,000 | Implemented |
LE0292 # 05 Y:2009 | 05 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,424 | $1,840 | Not Implemented |
LE0292 # 06 Y:2009 | 06 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,459 | $200 | Implemented |
LE0292 # 07 Y:2009 | 07 | 2009 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,073 | $3,000 | Implemented |
LE0292 # 08 Y:2009 | 08 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,952 | $1,000 | Not Implemented |
LE0292 # 09 Y:2009 | 09 | 2009 | INSTALL OCCUPANCY SENSORS | $961 | $420 | Implemented |
SU0286 # 01 Y:2009 | 01 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $11,756 | $0 | Implemented |
SU0286 # 02 Y:2009 | 02 | 2009 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $8,876 | $0 | Not Implemented |
SU0286 # 03 Y:2009 | 03 | 2009 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,389 | $0 | Not Implemented |
SU0286 # 04 Y:2009 | 04 | 2009 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,215 | $0 | Implemented |
SU0286 # 05 Y:2009 | 05 | 2009 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,974 | $0 | Not Implemented |
SU0286 # 06 Y:2009 | 06 | 2009 | DISCONNECT BALLASTS | $1,462 | $0 | Not Implemented |
SU0286 # 07 Y:2009 | 07 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,080 | $287 | Implemented |