Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,067
matching recommendationsNAICS | 3359 | Other Electrical Equipment and Component Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1020 # 05 Y:2020 | 05 | 2020 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $1,639 | $6,550 | Not Implemented |
UD1020 # 06 Y:2020 | 06 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,337 | $22,400 | Not Implemented |
UD1020 # 07 Y:2020 | 07 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $901 | $0 | Not Implemented |
UD1020 # 08 Y:2020 | 08 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $832 | $0 | Not Implemented |
OK1029 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,568 | $2,250 | Implemented |
OK1029 # 02 Y:2020 | 02 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,512 | $0 | Not Implemented |
OK1029 # 03 Y:2020 | 03 | 2020 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $4,684 | $22,100 | Implemented |
OK1029 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,197 | $30,672 | Implemented |
OK1029 # 05 Y:2020 | 05 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $546 | $522 | Not Implemented |
AS0487 # 01 Y:2020 | 01 | 2020 | INSTALL REFRIGERATION SYSTEM TO COOL PRODUCT | $502,983 | $7,794 | Not Implemented |
AS0487 # 02 Y:2020 | 02 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $51,986 | $394,050 | Not Implemented |
AS0487 # 03 Y:2020 | 03 | 2020 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $21,819 | $29,360 | Not Implemented |
AS0487 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,784 | $10,912 | Not Implemented |
AS0487 # 05 Y:2020 | 05 | 2020 | USE PHOTOCELL CONTROLS | $12,092 | $5,188 | Not Implemented |
LE0483 # 01 Y:2019 | 01 | 2019 | LOWER COMPRESSOR PRESSURE THROUGH A/C SYSTEM MODIFICATION | $200 | $40 | Implemented |
LE0483 # 02 Y:2019 | 02 | 2019 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $6,044 | $11,000 | Not Implemented |
LE0483 # 03 Y:2019 | 03 | 2019 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,352 | $12,000 | Not Implemented |
LE0483 # 04 Y:2019 | 04 | 2019 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $5,605 | $12,900 | Not Implemented |
LE0483 # 05 Y:2019 | 05 | 2019 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $4,574 | $20,000 | Implemented |
UF0536 # 01 Y:2019 | 01 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $10,130 | $557 | Not Implemented |
UF0536 # 02 Y:2019 | 02 | 2019 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $5,331 | $25,000 | Not Implemented |
UF0536 # 03 Y:2019 | 03 | 2019 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,433 | $2,264 | Not Implemented |
UF0536 # 04 Y:2019 | 04 | 2019 | CLEAN CONDENSER TUBES | $4,554 | $4,248 | Not Implemented |
UF0536 # 05 Y:2019 | 05 | 2019 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $25,860 | $33,265 | Not Implemented |
UF0536 # 06 Y:2019 | 06 | 2019 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $18,000 | $18,548 | Not Implemented |