Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
70
matching recommendationsNAICS | 3359 | Other Electrical Equipment and Component Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SJ0012 # 04 Y:2024 | 04 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $151,265 | $402,860 | Not Implemented |
SJ0012 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,511 | $11,438 | Not Implemented |
SJ0012 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $215 | $0 | Not Implemented |
SJ0012 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,778 | $22,286 | Implemented |
SJ0012 # 01 Y:2024 | 01 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $26 | $0 | Not Implemented |
SJ0012 # 06 Y:2024 | 06 | 2024 | USE MINIMUM SAFE OVEN VENTILATION | $157 | $217 | Not Implemented |
SJ0012 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,374 | $0 | Not Implemented |
SJ0002 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,309 | $22,700 | Implemented |
SJ0002 # 06 Y:2023 | 06 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,772 | $0 | Implemented |
SJ0002 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $72,623 | $275,269 | Not Implemented |
SJ0002 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,741 | $652 | Implemented |
SJ0002 # 03 Y:2023 | 03 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $424 | $194 | Implemented |
SJ0002 # 04 Y:2023 | 04 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,185 | $0 | Implemented |
SF0586 # 01 Y:2022 | 01 | 2022 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,887 | $0 | Implemented |
SF0586 # 08 Y:2022 | 08 | 2022 | REPLACE DC EQUIPMENT WITH AC EQUIPMENT | $62,090 | $317,631 | Implemented |
SF0586 # 07 Y:2022 | 07 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,736 | $14,830 | Implemented |
SF0586 # 06 Y:2022 | 06 | 2022 | INSULATE BARE EQUIPMENT | $1,974 | $4,260 | Implemented |
SF0586 # 05 Y:2022 | 05 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $35,916 | $68,135 | Implemented |
SF0586 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $38,428 | $26,487 | Implemented |
SF0586 # 03 Y:2022 | 03 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $38,078 | $22,361 | Implemented |
SF0586 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,868 | $0 | Implemented |
SD0599 # 03 Y:2020 | 03 | 2020 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,370 | $12,585 | Not Implemented |
SD0599 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,596 | $4,732 | Not Implemented |
SD0599 # 01 Y:2020 | 01 | 2020 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $12,200 | $33,000 | Not Implemented |
SD0599 # 02 Y:2020 | 02 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,284 | $8,600 | Not Implemented |