Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
58
matching recommendationsNAICS | 336 | Transportation Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0417 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,886 | $2,761 | Implemented |
TT0293 # 09 Y:2023 | 09 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $630 | $2,000 | Implemented |
TT0293 # 07 Y:2023 | 07 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $923 | $1,600 | Implemented |
TT0293 # 04 Y:2023 | 04 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,615 | $31,320 | Implemented |
TT0293 # 06 Y:2023 | 06 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,199 | $0 | Implemented |
TT0293 # 03 Y:2023 | 03 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $7,910 | $600 | Implemented |
TT0293 # 02 Y:2023 | 02 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $10,120 | $0 | Implemented |
TT0293 # 08 Y:2023 | 08 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $736 | $170 | Implemented |
TT0293 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,707 | $1,500 | Implemented |
TT0278 # 08 Y:2022 | 08 | 2022 | SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING | $2,362 | $2,736 | Implemented |
TT0278 # 04 Y:2022 | 04 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $5,912 | $18,000 | Implemented |
TT0278 # 07 Y:2022 | 07 | 2022 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $3,425 | $0 | Implemented |
TT0278 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,020 | $107,478 | Implemented |
TT0278 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,152 | $1,500 | Implemented |
LS1908 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $64,386 | $25,000 | Implemented |
LS1908 # 05 Y:2019 | 05 | 2019 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $46,800 | $30,000 | Implemented |
LS1908 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $31,396 | $21,120 | Implemented |
LS1908 # 01 Y:2019 | 01 | 2019 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $3,210 | $0 | Implemented |
UA0202 # 06 Y:2019 | 06 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,888 | $1,345 | Implemented |
UA0202 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $15,356 | $100 | Implemented |
UA0202 # 02 Y:2019 | 02 | 2019 | INSTALL OCCUPANCY SENSORS | $4,359 | $17,407 | Implemented |
UA0202 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,355 | $39,669 | Implemented |
UA0202 # 04 Y:2019 | 04 | 2019 | INSTALL TIMERS AND/OR THERMOSTATS | $29,377 | $15 | Implemented |
TT0212 # 04 Y:2018 | 04 | 2018 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $38,635 | $13,000 | Implemented |
TT0212 # 05 Y:2018 | 05 | 2018 | METER WASTE WATER | $34,128 | $1,900 | Implemented |