Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
777
matching recommendationsNAICS | 336 | Transportation Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1049 # 06 Y:2023 | 06 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $10,943 | $20,000 | Not Implemented |
UD1049 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,075 | $952 | Not Implemented |
UD1049 # 04 Y:2023 | 04 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $72,916 | $709 | Not Implemented |
UD1049 # 03 Y:2023 | 03 | 2023 | REDUCE VENTILATION AIR | $153,776 | $45,000 | Not Implemented |
UD1049 # 02 Y:2023 | 02 | 2023 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $9,224 | $0 | Not Implemented |
UD1049 # 01 Y:2023 | 01 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $10,825 | $0 | Implemented |
UL2214 # 01 Y:2022 | 01 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $67,238 | $1,046,392 | Not Implemented |
UL2214 # 02 Y:2022 | 02 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $43,721 | $432,345 | Not Implemented |
UL2214 # 03 Y:2022 | 03 | 2022 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,475 | $0 | Not Implemented |
UL2214 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $626 | $3,993 | Not Implemented |
UL2214 # 05 Y:2022 | 05 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,543 | $0 | Not Implemented |
UL2214 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,187 | $1,760 | Not Implemented |
UL2214 # 07 Y:2022 | 07 | 2022 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $612 | $0 | Not Implemented |
UD1046 # 14 Y:2022 | 14 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $386,941 | $554,028 | Implemented |
UD1046 # 13 Y:2022 | 13 | 2022 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $127,137 | $75,000 | Implemented |
UD1046 # 12 Y:2022 | 12 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,614 | $5,220 | Not Implemented |
UD1046 # 11 Y:2022 | 11 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,765 | $4,001 | Not Implemented |
UD1046 # 10 Y:2022 | 10 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,940 | $0 | Not Implemented |
UD1046 # 09 Y:2022 | 09 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $35,495 | $1,200 | Not Implemented |
UD1046 # 08 Y:2022 | 08 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $27,755 | $60,000 | Not Implemented |
UD1046 # 07 Y:2022 | 07 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,615 | $1,500 | Not Implemented |
UD1046 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $30,166 | $0 | Implemented |
UD1046 # 05 Y:2022 | 05 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,795 | $3,279 | Not Implemented |
UD1046 # 04 Y:2022 | 04 | 2022 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $43,076 | $3,500 | Implemented |
UD1046 # 03 Y:2022 | 03 | 2022 | IMPROVE COMBUSTION CONTROL CAPABILITY | $261,813 | $100 | Not Implemented |