Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,366
matching recommendationsNAICS | 3363 | Motor Vehicle Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0198 # 05 Y:2010 | 05 | 2010 | INSTALL OCCUPANCY SENSORS | $5,576 | $14,400 | Implemented |
MI0198 # 06 Y:2010 | 06 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,870 | $1,210 | Implemented |
MI0198 # 07 Y:2010 | 07 | 2010 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $3,644 | $11,985 | Not Implemented |
MI0198 # 08 Y:2010 | 08 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,407 | $40 | Implemented |
WV0415 # 01 Y:2010 | 01 | 2010 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $86,422 | $15,000 | Not Implemented |
WV0415 # 02 Y:2010 | 02 | 2010 | UPGRADE CONTROLS ON COMPRESSORS | $21,876 | $30,800 | Not Implemented |
WV0415 # 03 Y:2010 | 03 | 2010 | REDUCE VENTILATION AIR | $18,153 | $5,000 | Not Implemented |
WV0415 # 04 Y:2010 | 04 | 2010 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $14,296 | $7,820 | Implemented |
WV0415 # 05 Y:2010 | 05 | 2010 | USE RADIANT HEATER FOR SPOT HEATING | $12,353 | $34,050 | Not Implemented |
WV0415 # 06 Y:2010 | 06 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,767 | $1,503 | Implemented |
WV0415 # 07 Y:2010 | 07 | 2010 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,621 | $2,000 | Implemented |
WV0415 # 08 Y:2010 | 08 | 2010 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $5,733 | $700 | Implemented |
WV0415 # 09 Y:2010 | 09 | 2010 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $4,603 | $5,265 | Not Implemented |
WV0415 # 10 Y:2010 | 10 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,852 | $884 | Implemented |
WV0415 # 11 Y:2010 | 11 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,398 | $4,490 | Implemented |
WV0415 # 12 Y:2010 | 12 | 2010 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,032 | $1,312 | Implemented |
UA3002 # 01 Y:2010 | 01 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,042 | $4,063 | Not Implemented |
UA3002 # 02 Y:2010 | 02 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,184 | $640 | Not Implemented |
UA3002 # 03 Y:2010 | 03 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $258 | $600 | Not Implemented |
UA3002 # 04 Y:2010 | 04 | 2010 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $10,623 | $0 | Not Implemented |
UA3002 # 05 Y:2010 | 05 | 2010 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $10,185 | $0 | Not Implemented |
UA3001 # 01 Y:2010 | 01 | 2010 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $42,535 | $960 | Implemented |
UA3001 # 02 Y:2010 | 02 | 2010 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $22,945 | $37,030 | Not Implemented |
UA3001 # 03 Y:2010 | 03 | 2010 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,600 | $10,620 | Not Implemented |
UA3001 # 04 Y:2010 | 04 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,740 | $7,420 | Implemented |