Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
524
matching recommendationsNAICS | 33639 | Other Motor Vehicle Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0375 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,932 | $4,843 | Implemented |
MI0375 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,712 | $2,100 | Implemented |
GT0945 # 01 Y:2020 | 01 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $39,291 | $1,575 | Implemented |
GT0945 # 02 Y:2020 | 02 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,333 | $300 | Implemented |
GT0945 # 03 Y:2020 | 03 | 2020 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $13,180 | $2,000 | Implemented |
GT0945 # 04 Y:2020 | 04 | 2020 | INSULATE BARE EQUIPMENT | $5,988 | $1,504 | Implemented |
GT0945 # 06 Y:2020 | 06 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,320 | $23,111 | Implemented |
TT0237 # 10 Y:2020 | 10 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $520 | $760 | Implemented |
TT0237 # 09 Y:2020 | 09 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,896 | $10 | Implemented |
TT0237 # 08 Y:2020 | 08 | 2020 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,445 | $0 | Implemented |
TT0237 # 07 Y:2020 | 07 | 2020 | METER WASTE WATER | $6,876 | $2,000 | Implemented |
TT0237 # 05 Y:2020 | 05 | 2020 | INSTALL TIMERS AND/OR THERMOSTATS | $11,220 | $20 | Implemented |
TT0237 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,403 | $33,173 | Implemented |
TT0237 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $21,248 | $3,360 | Implemented |
CW0111 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $577 | $50 | Implemented |
CW0111 # 02 Y:2020 | 02 | 2020 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $1,231 | $200 | Implemented |
CW0111 # 04 Y:2020 | 04 | 2020 | INSTALL OCCUPANCY SENSORS | $1,147 | $3,000 | Implemented |
CW0111 # 06 Y:2020 | 06 | 2020 | USE DEIONIZED WATER IN UPSTREAM RINSE TANKS | $39,911 | $4,800 | Implemented |
CW0111 # 07 Y:2020 | 07 | 2020 | AVOID FROST FORMATION ON EVAPORATORS | $27,066 | $28,000 | Implemented |
WV0590 # 13 Y:2020 | 13 | 2020 | DEVELOP A REPAIR/REPLACE POLICY | $101 | $271 | Implemented |
WV0590 # 12 Y:2020 | 12 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $768 | $100 | Implemented |
WV0590 # 11 Y:2020 | 11 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,693 | $1,000 | Implemented |
WV0590 # 09 Y:2020 | 09 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,957 | $813 | Implemented |
WV0590 # 07 Y:2020 | 07 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,881 | $1,468 | Implemented |
WV0590 # 04 Y:2020 | 04 | 2020 | INSULATE BARE EQUIPMENT | $16,468 | $5,109 | Implemented |