Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
27
matching recommendationsNAICS | 33639 | Other Motor Vehicle Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0176 # 07 Y:2021 | 07 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,411 | $5,700 | Implemented |
UU0176 # 05 Y:2021 | 05 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,766 | $7,600 | Implemented |
UU0176 # 03 Y:2021 | 03 | 2021 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $29,753 | $10,400 | Implemented |
UU0176 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $94,747 | $42,608 | Implemented |
UU0170 # 06 Y:2020 | 06 | 2020 | INSULATE BARE EQUIPMENT | $676 | $440 | Implemented |
UU0170 # 04 Y:2020 | 04 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,521 | $150 | Implemented |
UU0170 # 02 Y:2020 | 02 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $13,868 | $2,000 | Implemented |
UU0170 # 01 Y:2020 | 01 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $18,825 | $21,841 | Implemented |
UU0157 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,321 | $68,567 | Implemented |
UU0157 # 02 Y:2019 | 02 | 2019 | OPTIMIZE PLANT POWER FACTOR | $2,079 | $4,000 | Implemented |
UU0157 # 03 Y:2019 | 03 | 2019 | USE RADIANT HEATER FOR SPOT HEATING | $12,670 | $22,920 | Implemented |
UU0157 # 04 Y:2019 | 04 | 2019 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,094 | $8,488 | Implemented |
UU0157 # 05 Y:2019 | 05 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $314 | $218 | Implemented |
UU0157 # 06 Y:2019 | 06 | 2019 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,916 | $3,800 | Implemented |
UU0157 # 07 Y:2019 | 07 | 2019 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,880 | $650 | Implemented |
UU0154 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $170,761 | $461,313 | Implemented |
UU0154 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,288 | $2,040 | Implemented |
UU0154 # 05 Y:2019 | 05 | 2019 | INSULATE BARE EQUIPMENT | $10,215 | $3,044 | Implemented |
UU0132 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,322 | $36,216 | Implemented |
UU0132 # 05 Y:2018 | 05 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,767 | $0 | Implemented |
UU0132 # 03 Y:2018 | 03 | 2018 | ADD AREA LIGHTING SWITCHES | $5,976 | $7,600 | Implemented |
UU0132 # 02 Y:2018 | 02 | 2018 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $11,946 | $600 | Implemented |
UU0066 # 07 Y:2004 | 07 | 2004 | PAY BILLS ON TIME TO AVOID LATE FEES | $414 | $0 | Implemented |
UU0066 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $241 | $45 | Implemented |
UU0066 # 03 Y:2004 | 03 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $84 | $310 | Implemented |