matching recommendationsNAICS | 336413 | Other Aircraft Parts and Auxiliary Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CI0019 # 04 Y:2023 | 04 | 2023 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $6,992 | $8,890 | n/a |
CI0019 # 05 Y:2023 | 05 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $1,769 | $3,500 | n/a |
CI0019 # 08 Y:2023 | 08 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $851 | $1,500 | n/a |
CI0019 # 07 Y:2023 | 07 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,159 | $1,500 | n/a |
CI0019 # 06 Y:2023 | 06 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,444 | $200 | n/a |
SF0597 # 03 Y:2023 | 03 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $53,882 | $13,192 | Implemented |
SF0597 # 04 Y:2023 | 04 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $706 | $200 | Not Implemented |
SF0597 # 05 Y:2023 | 05 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $322,164 | $2,251,041 | Implemented |
SF0597 # 02 Y:2023 | 02 | 2023 | ADD AREA LIGHTING SWITCHES | $11,388 | $100 | Implemented |
SF0597 # 01 Y:2023 | 01 | 2023 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,268 | $0 | Implemented |
CI0001 # 07 Y:2022 | 07 | 2022 | USE PHOTOCELL CONTROLS | $1,147 | $1,440 | Not Implemented |
CI0001 # 02 Y:2022 | 02 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $16,299 | $3,500 | Not Implemented |
CI0001 # 06 Y:2022 | 06 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,304 | $25 | Not Implemented |
CI0001 # 05 Y:2022 | 05 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,000 | $5,000 | Not Implemented |
CI0001 # 04 Y:2022 | 04 | 2022 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,151 | $100 | Not Implemented |
CI0001 # 03 Y:2022 | 03 | 2022 | RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT | $5,122 | $6,000 | Not Implemented |
CI0001 # 01 Y:2022 | 01 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $27,056 | $750 | Implemented |
SD0613 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,201 | $1,065 | Implemented |
SD0613 # 02 Y:2021 | 02 | 2021 | SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING | $8,370 | $5,000 | Implemented |
SD0613 # 04 Y:2021 | 04 | 2021 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $590 | $1,500 | Not Implemented |
SD0613 # 01 Y:2021 | 01 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $7,677 | $16,500 | Implemented |
SD0613 # 05 Y:2021 | 05 | 2021 | INSTALL OCCUPANCY SENSORS | $218 | $2,500 | Implemented |
SD0605 # 05 Y:2020 | 05 | 2020 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $2,344 | $100 | Not Implemented |
SD0605 # 07 Y:2020 | 07 | 2020 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $639 | $2,000 | Not Implemented |
SD0605 # 04 Y:2020 | 04 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,760 | $1,855 | Not Implemented |