IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

979

matching recommendations
Reset
NAICS 336413 Other Aircraft Parts and Auxiliary Equipment Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CI0001 # 01 Y:2022 01 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $27,056 $750 Implemented
CI0001 # 02 Y:2022 02 2022 RECOVER WASTE HEAT FROM EQUIPMENT $16,299 $3,500 Not Implemented
CI0001 # 03 Y:2022 03 2022 RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT $5,122 $6,000 Not Implemented
CI0001 # 04 Y:2022 04 2022 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $2,151 $100 Not Implemented
CI0001 # 05 Y:2022 05 2022 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,000 $5,000 Not Implemented
CI0001 # 06 Y:2022 06 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,304 $25 Not Implemented
CI0001 # 07 Y:2022 07 2022 USE PHOTOCELL CONTROLS $1,147 $1,440 Not Implemented
UF0578 # 05 Y:2022 05 2022 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $7,688 $0 Implemented
UF0578 # 06 Y:2022 06 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,461 $390 Implemented
UF0578 # 07 Y:2022 07 2022 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,930 $0 Implemented
UF0578 # 08 Y:2022 08 2022 INSTALL OCCUPANCY SENSORS $1,065 $1,710 Implemented
UF0578 # 01 Y:2022 01 2022 USE DEMAND CONTROLLER OR LOAD SHEDDER $15,842 $11,742 Implemented
UF0578 # 02 Y:2022 02 2022 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS $12,457 $4,590 Not Implemented
UF0578 # 03 Y:2022 03 2022 RECOVER WASTE HEAT FROM EQUIPMENT $9,829 $2,419 Implemented
UF0578 # 04 Y:2022 04 2022 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $8,565 $25,400 Not Implemented
AS0517 # 01 Y:2022 01 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $47,690 $126,497 Not Implemented
AS0517 # 02 Y:2022 02 2022 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $11,446 $48,382 Not Implemented
AS0517 # 03 Y:2022 03 2022 USE OPTIMUM THICKNESS INSULATION $10,522 $15,516 Implemented
AS0517 # 04 Y:2022 04 2022 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $8,331 $39,600 Implemented
AS0517 # 05 Y:2022 05 2022 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $2,692 $2,880 Not Implemented
AS0517 # 06 Y:2022 06 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,189 $859 Implemented
AS0517 # 07 Y:2022 07 2022 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,256 $1,541 Implemented
CW0120 # 01 Y:2021 01 2021 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $30,000 $70,084 Implemented
CW0120 # 02 Y:2021 02 2021 INSTALL BACK-UP EQUIPMENT $32,054 $93,000 Implemented
CW0120 # 03 Y:2021 03 2021 USE BATTERY STORAGE FOR DEMAND CONTROL $18,089 $25,885 Implemented