Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
79
matching recommendationsNAICS | 336991 | Motorcycle, Bicycle, and Parts Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW2214 # 01 Y:2022 | 01 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,351 | $2,080 | Not Implemented |
UW2214 # 03 Y:2022 | 03 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,014 | $0 | Not Implemented |
UW2214 # 02 Y:2022 | 02 | 2022 | INSTALL OCCUPANCY SENSORS | $843 | $970 | Not Implemented |
UD1021 # 09 Y:2020 | 09 | 2020 | INSTALL OCCUPANCY SENSORS | $16,106 | $2,800 | Implemented |
UD1021 # 01 Y:2020 | 01 | 2020 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $10,283 | $0 | Implemented |
UD1021 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,841 | $0 | Implemented |
UD1021 # 04 Y:2020 | 04 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,342 | $0 | Implemented |
UD1021 # 06 Y:2020 | 06 | 2020 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,902 | $2,000 | Implemented |
UD1021 # 08 Y:2020 | 08 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,419 | $37,053 | Implemented |
UD1021 # 03 Y:2020 | 03 | 2020 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $5,965 | $1,400 | Not Implemented |
UD1021 # 07 Y:2020 | 07 | 2020 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $8,594 | $1,590 | Not Implemented |
UD1021 # 02 Y:2020 | 02 | 2020 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $32,724 | $0 | Implemented |
UD1021 # 10 Y:2020 | 10 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,902 | $7,800 | Not Implemented |
UD1021 # 11 Y:2020 | 11 | 2020 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $249 | $240 | Not Implemented |
UD0906 # 07 Y:2014 | 07 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,271 | $1,000 | Implemented |
UD0906 # 09 Y:2014 | 09 | 2014 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $58,357 | $14,000 | Not Implemented |
UD0906 # 03 Y:2014 | 03 | 2014 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,503 | $0 | Implemented |
UD0906 # 06 Y:2014 | 06 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,456 | $5,614 | Implemented |
UD0906 # 01 Y:2014 | 01 | 2014 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $17,248 | $0 | Not Implemented |
UD0906 # 02 Y:2014 | 02 | 2014 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,093 | $0 | Implemented |
UD0906 # 08 Y:2014 | 08 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $618 | $0 | Not Implemented |
UD0906 # 05 Y:2014 | 05 | 2014 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $5,162 | $10,000 | Not Implemented |
UD0906 # 04 Y:2014 | 04 | 2014 | INSTALL OCCUPANCY SENSORS | $2,954 | $1,575 | Implemented |
IP0016 # 06 Y:2013 | 06 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $19,081 | $21,876 | Not Implemented |
IP0016 # 05 Y:2013 | 05 | 2013 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $3,008 | $797 | Not Implemented |