Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
230
matching recommendationsNAICS | 3391 | Medical Equipment and Supplies Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0516 # 06 Y:2018 | 06 | 2018 | INSTALL EQUIPMENT TO MOVE PRODUCT | $30,207 | $5,350 | Not Implemented |
UF0516 # 07 Y:2018 | 07 | 2018 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $23,725 | $10,695 | Not Implemented |
MI0282 # 01 Y:2015 | 01 | 2015 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $23,744 | $1,120 | Not Implemented |
MI0282 # 02 Y:2015 | 02 | 2015 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $11,822 | $10,322 | Implemented |
MI0282 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,613 | $1,660 | Implemented |
MI0282 # 04 Y:2015 | 04 | 2015 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,005 | $1,220 | Not Implemented |
MI0282 # 05 Y:2015 | 05 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,694 | $40 | Not Implemented |
MI0282 # 06 Y:2015 | 06 | 2015 | REDUCE HEAT GAIN BY WINDOW TINTING | $3,779 | $16,060 | Not Implemented |
MI0282 # 07 Y:2015 | 07 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,378 | $40 | Implemented |
MI0282 # 08 Y:2015 | 08 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,655 | $1,080 | Implemented |
MI0282 # 09 Y:2015 | 09 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,303 | $5,120 | Implemented |
MI0282 # 10 Y:2015 | 10 | 2015 | INSTALL OCCUPANCY SENSORS | $1,250 | $995 | Implemented |
MI0282 # 11 Y:2015 | 11 | 2015 | USE PHOTOCELL CONTROLS | $197 | $600 | Implemented |
MI0282 # 12 Y:2015 | 12 | 2015 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $50 | $85 | Not Implemented |
MI0280 # 01 Y:2015 | 01 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $7,699 | $1,400 | Implemented |
MI0280 # 02 Y:2015 | 02 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $7,149 | $2,100 | Implemented |
MI0280 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,428 | $1,660 | Implemented |
MI0280 # 04 Y:2015 | 04 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,213 | $40 | Not Implemented |
MI0280 # 05 Y:2015 | 05 | 2015 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,213 | $4,750 | Implemented |
MI0280 # 06 Y:2015 | 06 | 2015 | INSTALL OCCUPANCY SENSORS | $1,053 | $332 | Implemented |
MI0280 # 07 Y:2015 | 07 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $797 | $3,520 | Implemented |
MI0280 # 08 Y:2015 | 08 | 2015 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $393 | $220 | Implemented |
MI0280 # 09 Y:2015 | 09 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $233 | $375 | Implemented |
MI0259 # 01 Y:2014 | 01 | 2014 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $15,289 | $80 | Not Implemented |
MI0259 # 02 Y:2014 | 02 | 2014 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $9,010 | $8,479 | Implemented |