Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
50
matching recommendationsNAICS | 3399 | Other Miscellaneous Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0350 # 05 Y:2004 | 05 | 2004 | ADD AREA LIGHTING SWITCHES | $11,915 | $500 | Implemented |
SD0350 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,013 | $20,872 | Implemented |
SD0350 # 03 Y:2004 | 03 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,353 | $1,650 | Implemented |
SD0350 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,815 | $250 | Implemented |
SD0350 # 01 Y:2004 | 01 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,900 | $0 | Implemented |
WV0307 # 03 Y:2004 | 03 | 2004 | ISOLATE HOT OR COLD EQUIPMENT | $3,113 | $755 | Implemented |
WV0307 # 14 Y:2004 | 14 | 2004 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $1,224 | $140 | Implemented |
WV0307 # 12 Y:2004 | 12 | 2004 | USE OPTIMUM THICKNESS INSULATION | $278 | $380 | Implemented |
WV0307 # 11 Y:2004 | 11 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $903 | $0 | Implemented |
WV0307 # 10 Y:2004 | 10 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $1,513 | $271 | Implemented |
WV0307 # 09 Y:2004 | 09 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,177 | $210 | Implemented |
WV0307 # 08 Y:2004 | 08 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,767 | $53 | Implemented |
WV0307 # 13 Y:2004 | 13 | 2004 | INSULATE BARE EQUIPMENT | $262 | $260 | Implemented |
BD0267 # 10 Y:2004 | 10 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $173 | $292 | Implemented |
BD0267 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $818 | $60 | Implemented |
BD0267 # 06 Y:2004 | 06 | 2004 | INSTALL OCCUPANCY SENSORS | $749 | $720 | Implemented |
BD0267 # 07 Y:2004 | 07 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $364 | $0 | Implemented |
BD0267 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $234 | $210 | Implemented |
BD0267 # 11 Y:2004 | 11 | 2004 | USE SYNTHETIC LUBRICANT | $124 | $30 | Implemented |
BD0267 # 12 Y:2004 | 12 | 2004 | CONVERT TO ELECTROSTATIC POWDER COATING | $11,120 | $5,174 | Implemented |
UU0065 # 04 Y:2004 | 04 | 2004 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,188 | $225 | Implemented |
UU0065 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,345 | $1,100 | Implemented |
UU0065 # 02 Y:2004 | 02 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,450 | $0 | Implemented |
LE0177 # 03 Y:2004 | 03 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,194 | $0 | Implemented |
LE0177 # 04 Y:2004 | 04 | 2004 | USE OPTIMUM THICKNESS INSULATION | $516 | $585 | Implemented |