IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,372

matching recommendations
Reset
NAICS 3399 Other Miscellaneous Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SU0193 # 03 Y:2004 03 2004 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $2,396 $0 Implemented
SU0193 # 04 Y:2004 04 2004 USE SYNTHETIC LUBRICANT $1,343 $200 Implemented
SU0193 # 05 Y:2004 05 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $942 $363 Implemented
SU0193 # 06 Y:2004 06 2004 RECOVER WASTE HEAT FROM EQUIPMENT $489 $304 Implemented
SU0193 # 07 Y:2004 07 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,158 $2,415 Not Implemented
SU0193 # 08 Y:2004 08 2004 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $4,989 $10,421 Implemented
SU0193 # 09 Y:2004 09 2004 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $3,340 $10,000 Not Implemented
SD0350 # 01 Y:2004 01 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,900 $0 Implemented
SD0350 # 02 Y:2004 02 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,815 $250 Implemented
SD0350 # 03 Y:2004 03 2004 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,353 $1,650 Implemented
SD0350 # 04 Y:2004 04 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,013 $20,872 Implemented
SD0350 # 05 Y:2004 05 2004 ADD AREA LIGHTING SWITCHES $11,915 $500 Implemented
WV0307 # 01 Y:2004 01 2004 USE RADIANT HEATER FOR SPOT HEATING $33,386 $16,600 Not Implemented
WV0307 # 02 Y:2004 02 2004 MINIMIZE WATER USAGE $9,168 $7,800 Not Implemented
WV0307 # 03 Y:2004 03 2004 ISOLATE HOT OR COLD EQUIPMENT $3,113 $755 Implemented
WV0307 # 04 Y:2004 04 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,891 $4,040 Not Implemented
WV0307 # 05 Y:2004 05 2004 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $2,255 $1,505 Not Implemented
WV0307 # 06 Y:2004 06 2004 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,120 $600 Not Implemented
WV0307 # 07 Y:2004 07 2004 RECOVER WASTE HEAT FROM EQUIPMENT $1,956 $1,260 Not Implemented
WV0307 # 08 Y:2004 08 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,767 $53 Implemented
WV0307 # 09 Y:2004 09 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,177 $210 Implemented
WV0307 # 10 Y:2004 10 2004 DEVELOP A REPAIR/REPLACE POLICY $1,513 $271 Implemented
WV0307 # 11 Y:2004 11 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $903 $0 Implemented
WV0307 # 12 Y:2004 12 2004 USE OPTIMUM THICKNESS INSULATION $278 $380 Implemented
WV0307 # 13 Y:2004 13 2004 INSULATE BARE EQUIPMENT $262 $260 Implemented