IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

24

matching recommendations
Reset
NAICS 33999 All Other Miscellaneous Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LE0441 # 02 Y:2017 02 2017 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,114 $20 Implemented
LE0441 # 03 Y:2017 03 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,738 $1,000 Implemented
LE0441 # 04 Y:2017 04 2017 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $57,323 $15,000 Not Implemented
LE0441 # 05 Y:2017 05 2017 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $831 $1,000 Not Implemented
LE0441 # 06 Y:2017 06 2017 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $9,845 $16,000 Not Implemented
LE0441 # 07 Y:2017 07 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $780 $2,067 Implemented
LE0441 # 08 Y:2017 08 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,133 $9,520 Implemented
LE0441 # 01 Y:2017 01 2017 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $4,712 $20 Not Implemented
DL0112 # 07 Y:2013 07 2013 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $12,700 $33,000 Not Implemented
DL0112 # 06 Y:2013 06 2013 UPGRADE CONTROLS ON COMPRESSORS $32,800 $16,000 Not Implemented
DL0112 # 05 Y:2013 05 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $21,034 $13,739 Implemented
DL0112 # 04 Y:2013 04 2013 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $4,800 $5,850 Not Implemented
DL0112 # 03 Y:2013 03 2013 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $8,900 $40,000 Implemented
DL0112 # 02 Y:2013 02 2013 REPLACE STEAM JETS ON VACUUM SYSTEM WITH ELECTRIC MOTOR DRIVEN VACUUM PUMPS $8,930 $2,820 Not Implemented
DL0112 # 01 Y:2013 01 2013 RECOVER WASTE HEAT FROM EQUIPMENT $48,700 $2,341 Not Implemented
DL0016 # 08 Y:2008 08 2008 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $38,540 $125,000 Not Implemented
DL0016 # 09 Y:2008 09 2008 USE SOLAR HEAT TO MAKE ELECTRICTY $15,600 $600,000 Not Implemented
DL0016 # 07 Y:2008 07 2008 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $24 $2,394 Implemented
DL0016 # 06 Y:2008 06 2008 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $635 $160 Not Implemented
DL0016 # 05 Y:2008 05 2008 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,304 $500 Not Implemented
DL0016 # 04 Y:2008 04 2008 INSTALL OCCUPANCY SENSORS $3,343 $590 Implemented
DL0016 # 03 Y:2008 03 2008 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $11,172 $700 Not Implemented
DL0016 # 02 Y:2008 02 2008 TURN OFF EQUIPMENT WHEN NOT IN USE $12,550 $0 Implemented
DL0016 # 01 Y:2008 01 2008 UPGRADE CONTROLS ON COMPRESSORS $19,500 $1,000 Not Implemented