Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
42
matching recommendationsNAICS | 721 | Accommodation |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MUCM18 # 05 Y:2024 | 05 | 2024 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $63 | $0 | Implemented |
MUCM18 # 07 Y:2024 | 07 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $165 | $0 | Implemented |
MUCM18 # 01 Y:2024 | 01 | 2024 | USE OPTIMUM TEMPERATURE | $259 | $0 | Implemented |
MUCM18 # 03 Y:2024 | 03 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $151 | $717 | Implemented |
MUCM18 # 04 Y:2024 | 04 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $265 | $567 | Implemented |
UU0243 # 03 Y:2024 | 03 | 2024 | COVER OPEN TANKS | $9,190 | $7,340 | Implemented |
UU0243 # 01 Y:2024 | 01 | 2024 | AIR CONDITION ONLY SPACE NECESSARY | $26,330 | $19,500 | Implemented |
UU0243 # 06 Y:2024 | 06 | 2024 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $2,800 | $6,300 | Implemented |
UU0243 # 07 Y:2024 | 07 | 2024 | OPTIMIZE PLANT POWER FACTOR | $1,900 | $6,000 | Implemented |
LS2023 # 06 Y:2023 | 06 | 2023 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $193,754 | $552,840 | Implemented |
LS2023 # 05 Y:2023 | 05 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,548 | $14,800 | Implemented |
LS2023 # 01 Y:2023 | 01 | 2023 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $56,174 | $1,000 | Implemented |
AS0563 # 04 Y:2023 | 04 | 2023 | ADJUST BURNERS FOR EFFICIENT OPERATION | $4,800 | $481 | Implemented |
AS0563 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,261 | $14,447 | Implemented |
AS0563 # 01 Y:2023 | 01 | 2023 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $24,380 | $2,114 | Implemented |
LT8378 # 05 Y:2023 | 05 | 2023 | INSTALL OCCUPANCY SENSORS | $2,353 | $10,050 | Implemented |
LT8378 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $869 | $864 | Implemented |
LT8378 # 01 Y:2023 | 01 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $11,552 | $30,450 | Implemented |
AS0551 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $784 | $3,277 | Implemented |
AS0551 # 02 Y:2023 | 02 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,528 | $7,174 | Implemented |
AS0551 # 03 Y:2023 | 03 | 2023 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,477 | $3,284 | Implemented |
AS0551 # 05 Y:2023 | 05 | 2023 | USE PHOTOCELL CONTROLS | $378 | $819 | Implemented |
AS0551 # 01 Y:2023 | 01 | 2023 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $2,434 | $2,202 | Implemented |
LS0123 # 02 Y:2023 | 02 | 2023 | REPLACE BOILER | $17,372 | $62,400 | Implemented |
LS0123 # 01 Y:2023 | 01 | 2023 | INSTALL OCCUPANCY SENSORS | $106 | $157 | Implemented |