Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
26
matching recommendationsNAICS | 721110 | Hotels (except Casino Hotels) and Motels |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0243 # 07 Y:2024 | 07 | 2024 | OPTIMIZE PLANT POWER FACTOR | $1,900 | $6,000 | Implemented |
UU0243 # 06 Y:2024 | 06 | 2024 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $2,800 | $6,300 | Implemented |
UU0243 # 03 Y:2024 | 03 | 2024 | COVER OPEN TANKS | $9,190 | $7,340 | Implemented |
UU0243 # 01 Y:2024 | 01 | 2024 | AIR CONDITION ONLY SPACE NECESSARY | $26,330 | $19,500 | Implemented |
LS2023 # 06 Y:2023 | 06 | 2023 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $193,754 | $552,840 | Implemented |
LS2023 # 05 Y:2023 | 05 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,548 | $14,800 | Implemented |
LS2023 # 01 Y:2023 | 01 | 2023 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $56,174 | $1,000 | Implemented |
AS0563 # 01 Y:2023 | 01 | 2023 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $24,380 | $2,114 | Implemented |
AS0563 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,261 | $14,447 | Implemented |
AS0563 # 04 Y:2023 | 04 | 2023 | ADJUST BURNERS FOR EFFICIENT OPERATION | $4,800 | $481 | Implemented |
AS0551 # 02 Y:2023 | 02 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,528 | $7,174 | Implemented |
AS0551 # 05 Y:2023 | 05 | 2023 | USE PHOTOCELL CONTROLS | $378 | $819 | Implemented |
AS0551 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $784 | $3,277 | Implemented |
AS0551 # 03 Y:2023 | 03 | 2023 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,477 | $3,284 | Implemented |
AS0551 # 01 Y:2023 | 01 | 2023 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $2,434 | $2,202 | Implemented |
LS0123 # 03 Y:2023 | 03 | 2023 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $14,146 | $54,880 | Implemented |
LS0123 # 02 Y:2023 | 02 | 2023 | REPLACE BOILER | $17,372 | $62,400 | Implemented |
LS0123 # 01 Y:2023 | 01 | 2023 | INSTALL OCCUPANCY SENSORS | $106 | $157 | Implemented |
LS1922 # 01 Y:2022 | 01 | 2022 | INSTALL OCCUPANCY SENSORS | $2,632 | $375 | Implemented |
LS1922 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,968 | $10,554 | Implemented |
LS1822 # 01 Y:2022 | 01 | 2022 | REDUCE HEAT GAIN BY WINDOW TINTING | $30,799 | $2,056 | Implemented |
LS1822 # 04 Y:2022 | 04 | 2022 | INSTALL OCCUPANCY SENSORS | $49 | $50 | Implemented |
LS1822 # 05 Y:2022 | 05 | 2022 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $6,150 | $23,430 | Implemented |
LS1722 # 01 Y:2022 | 01 | 2022 | PAY BILLS ON TIME TO AVOID LATE FEES | $3,204 | $0 | Implemented |
LS1722 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,524 | $1,910 | Implemented |