Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,261
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0633 # 07 Y:2023 | 07 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $28,972 | $66,845 | Implemented |
SD0633 # 04 Y:2023 | 04 | 2023 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $372,017 | $505,200 | Implemented |
SD0633 # 08 Y:2023 | 08 | 2023 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $102,944 | $0 | Implemented |
SD0633 # 05 Y:2023 | 05 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,338 | $500 | Implemented |
SD0633 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $32,814 | $77,773 | Implemented |
SD0633 # 01 Y:2023 | 01 | 2023 | DEVELOP A REPAIR/REPLACE POLICY | $1,124 | $98 | Implemented |
SD0633 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $680 | $1,830 | Implemented |
SF0598 # 02 Y:2023 | 02 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,805 | $1,551 | Implemented |
SF0598 # 01 Y:2023 | 01 | 2023 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $10,131 | $0 | Implemented |
SF0598 # 05 Y:2023 | 05 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $5,883 | $23,100 | Implemented |
SF0598 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,843 | $8,505 | Implemented |
SF0596 # 01 Y:2023 | 01 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,903 | $1,551 | Implemented |
SF0596 # 04 Y:2023 | 04 | 2023 | INSULATE BARE EQUIPMENT | $1,185 | $2,397 | Implemented |
SF0596 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,982 | $4,346 | Implemented |
SF0596 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,166 | $9,707 | Implemented |
SF0595 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,469 | $5,620 | Implemented |
SF0595 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,989 | $21,654 | Implemented |
SF0595 # 02 Y:2023 | 02 | 2023 | USE OPTIMUM THICKNESS INSULATION | $2,174 | $1,800 | Implemented |
SF0595 # 06 Y:2023 | 06 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,280 | $7,191 | Implemented |
SF0595 # 01 Y:2023 | 01 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $5,809 | $1,487 | Implemented |
SF0591 # 02 Y:2022 | 02 | 2022 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $9,922 | $0 | Implemented |
SF0591 # 03 Y:2022 | 03 | 2022 | REDUCE EXCESS STEAM BLEEDING | $9,616 | $0 | Implemented |
SF0591 # 07 Y:2022 | 07 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,540 | $14,724 | Implemented |
SF0591 # 04 Y:2022 | 04 | 2022 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $6,698 | $0 | Implemented |
SF0591 # 06 Y:2022 | 06 | 2022 | INSTALL SET-BACK TIMERS | $22,648 | $6,467 | Implemented |