Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
290
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0659 # 02 Y:2015 | 02 | 2015 | MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT | $26,260 | $7,200 | Implemented |
OR0659 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,705 | $20,000 | Implemented |
IP0048 # 10 Y:2015 | 10 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $116 | $413 | Implemented |
IP0048 # 02 Y:2015 | 02 | 2015 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $16,379 | $5 | Implemented |
IP0048 # 09 Y:2015 | 09 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,176 | $8,753 | Implemented |
IP0048 # 03 Y:2015 | 03 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,718 | $5 | Implemented |
IP0048 # 04 Y:2015 | 04 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $902 | $45 | Implemented |
IP0048 # 05 Y:2015 | 05 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,880 | $430 | Implemented |
OK0926 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,480 | $22,750 | Implemented |
UK1511 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,582 | $51,370 | Implemented |
UK1511 # 04 Y:2015 | 04 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $596 | $0 | Implemented |
UK1511 # 03 Y:2015 | 03 | 2015 | OPTIMIZE PLANT POWER FACTOR | $9,011 | $8,260 | Implemented |
UK1511 # 01 Y:2015 | 01 | 2015 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $457,639 | $1,000,000 | Implemented |
UK1511 # 14 Y:2015 | 14 | 2015 | INSULATE FEEDWATER TANK | $1,113 | $862 | Implemented |
UK1511 # 11 Y:2015 | 11 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $552 | $0 | Implemented |
UK1511 # 09 Y:2015 | 09 | 2015 | UPGRADE OBSOLETE EQUIPMENT | $2,127 | $14,000 | Implemented |
UK1511 # 06 Y:2015 | 06 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,159 | $1,371 | Implemented |
UK1511 # 08 Y:2015 | 08 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $737 | $1,500 | Implemented |
UK1511 # 07 Y:2015 | 07 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,050 | $0 | Implemented |
IP0047 # 01 Y:2015 | 01 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,458 | $163 | Implemented |
IP0047 # 05 Y:2015 | 05 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $30,801 | $10,000 | Implemented |
IP0047 # 06 Y:2015 | 06 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $10,288 | $5,000 | Implemented |
SF0474 # 07 Y:2015 | 07 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,353 | $39,333 | Implemented |
SF0474 # 04 Y:2015 | 04 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $26,501 | $5,010 | Implemented |
SF0474 # 10 Y:2015 | 10 | 2015 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $7,060 | $29,463 | Implemented |