Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
381
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0341 # 01 Y:2023 | 01 | 2023 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $18,080 | $9,000 | Not Implemented |
MZ0341 # 04 Y:2023 | 04 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,207 | $160 | Not Implemented |
MZ0341 # 03 Y:2023 | 03 | 2023 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $12,536 | $16,400 | Not Implemented |
MZ0341 # 02 Y:2023 | 02 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $13,839 | $3,000 | Not Implemented |
TT0291 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,663 | $1,500 | Implemented |
TT0291 # 06 Y:2023 | 06 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $2,088 | $4,500 | Not Implemented |
TT0291 # 03 Y:2023 | 03 | 2023 | PURCHASE APPROPRIATELY SIZED MATERIAL | $18,022 | $87,000 | Not Implemented |
TT0291 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $41,378 | $10,100 | Implemented |
TT0291 # 04 Y:2023 | 04 | 2023 | USE OPTIMUM THICKNESS INSULATION | $14,929 | $45,390 | Not Implemented |
TT0291 # 01 Y:2023 | 01 | 2023 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $44,264 | $3,287 | Not Implemented |
LT8363 # 02 Y:2022 | 02 | 2022 | CHANGE OPERATING CONDITIONS | $46,622 | $0 | n/a |
LT8363 # 07 Y:2022 | 07 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,254 | $0 | n/a |
LT8363 # 06 Y:2022 | 06 | 2022 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $23,817 | $51,385 | n/a |
LT8363 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,542 | $2,945 | n/a |
LT8363 # 01 Y:2022 | 01 | 2022 | OPTIMIZE PLANT POWER FACTOR | $5,980 | $10,022 | n/a |
LT8363 # 04 Y:2022 | 04 | 2022 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $14,468 | $15,975 | n/a |
LT8363 # 05 Y:2022 | 05 | 2022 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $22,308 | $32,500 | n/a |
OK0953 # 03 Y:2016 | 03 | 2016 | INSTALL OCCUPANCY SENSORS | $6,882 | $3,675 | Not Implemented |
OK0953 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,120 | $11,488 | Implemented |
OK0953 # 01 Y:2016 | 01 | 2016 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,868 | $150 | Not Implemented |
OK0953 # 04 Y:2016 | 04 | 2016 | USE RADIANT HEATER FOR SPOT HEATING | $9,116 | $27,880 | Not Implemented |
OK0926 # 03 Y:2015 | 03 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $11,134 | $0 | Not Implemented |
OK0926 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,480 | $22,750 | Implemented |
OK0926 # 01 Y:2015 | 01 | 2015 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $8,746 | $28,000 | Not Implemented |
OK0926 # 04 Y:2015 | 04 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $37,061 | $100,000 | Not Implemented |