IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

442

matching recommendations
Reset
SIC 20 Food and Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0144 # 07 Y:1989 07 1989 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $678 $200 Implemented
CO0144 # 08 Y:1989 08 1989 INSTALL TIMERS AND/OR THERMOSTATS $500 $450 Implemented
CO0144 # 09 Y:1989 09 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $214 $267 Implemented
OK0277 # 01 Y:1989 01 1989 INSULATE FEEDWATER TANK $344 $212 Implemented
OK0277 # 02 Y:1989 02 1989 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $4,470 $775 Not Implemented
OK0277 # 03 Y:1989 03 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $2,198 $1,500 Implemented
OK0277 # 04 Y:1989 04 1989 OPTIMIZE PLANT POWER FACTOR $1,069 $3,000 Not Implemented
OK0277 # 05 Y:1989 05 1989 RECOVER WASTE HEAT FROM EQUIPMENT $8,135 $18,000 Not Implemented
OK0277 # 06 Y:1989 06 1989 AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM $4,340 $12,000 Implemented
OK0277 # 07 Y:1989 07 1989 INSTALL TIMERS AND/OR THERMOSTATS $2,801 $250 Not Implemented
OK0277 # 08 Y:1989 08 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,430 $834 Implemented
OK0277 # 09 Y:1989 09 1989 INSTALL SET-BACK TIMERS $1,149 $1,440 Not Implemented
OK0277 # 10 Y:1989 10 1989 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS $10,418 $3,100 Not Implemented
WI0050 # 01 Y:1989 01 1989 IMPROVE LUBRICATION PRACTICES $4,124 $0 Not Implemented
WI0050 # 02 Y:1989 02 1989 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $821 $0 Not Implemented
WI0050 # 03 Y:1989 03 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $84 $713 Not Implemented
WI0050 # 04 Y:1989 04 1989 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $9,651 $0 Not Implemented
WI0050 # 05 Y:1989 05 1989 USE DEMAND CONTROLLER OR LOAD SHEDDER $2,920 $0 Not Implemented
WI0050 # 06 Y:1989 06 1989 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $3,290 $6,000 Not Implemented
WI0050 # 07 Y:1989 07 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $325 $500 Not Implemented
WI0050 # 08 Y:1989 08 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $957 $5,000 Not Implemented
WI0050 # 09 Y:1989 09 1989 HEAT WATER WITH EXHAUST HEAT $5,408 $10,000 Not Implemented
AM0056 # 01 Y:1989 01 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $4,790 $7,577 Not Implemented
AM0056 # 02 Y:1989 02 1989 RECOVER WASTE HEAT FROM EQUIPMENT $1,070 $700 Implemented
AM0056 # 03 Y:1989 03 1989 INSTALL SET-BACK TIMERS $970 $0 Implemented