Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,706
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0791 # 12 Y:2010 | 12 | 2010 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $655 | $0 | Not Implemented |
OK0791 # 13 Y:2010 | 13 | 2010 | INSTALL SET-BACK TIMERS | $684 | $1,024 | Not Implemented |
OR0556 # 01 Y:2010 | 01 | 2010 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $542 | $0 | Implemented |
OR0556 # 02 Y:2010 | 02 | 2010 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $1,765 | $0 | Not Implemented |
OR0556 # 03 Y:2010 | 03 | 2010 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $8,900 | $8,900 | Implemented |
OR0556 # 04 Y:2010 | 04 | 2010 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,987 | $5,125 | Not Implemented |
OR0556 # 05 Y:2010 | 05 | 2010 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $3,131 | $2,861 | Implemented |
OR0556 # 06 Y:2010 | 06 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,320 | $2,320 | Implemented |
OR0556 # 07 Y:2010 | 07 | 2010 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,397 | $11,734 | Not Implemented |
OR0556 # 08 Y:2010 | 08 | 2010 | USE SOLAR HEAT TO MAKE ELECTRICTY | $16,479 | $65,003 | Not Implemented |
MA0664 # 01 Y:2010 | 01 | 2010 | OPTIMIZE PLANT POWER FACTOR | $133,570 | $55,950 | Implemented |
MA0664 # 02 Y:2010 | 02 | 2010 | MINIMIZE WATER USAGE | $26,438 | $62,000 | Not Implemented |
MA0664 # 03 Y:2010 | 03 | 2010 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $25,051 | $34,000 | Not Implemented |
MA0664 # 04 Y:2010 | 04 | 2010 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $17,890 | $95,000 | Not Implemented |
MA0664 # 05 Y:2010 | 05 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,874 | $18,345 | Not Implemented |
MA0664 # 06 Y:2010 | 06 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,084 | $200 | Implemented |
SF0386 # 01 Y:2010 | 01 | 2010 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $10,471 | $0 | Not Implemented |
SF0386 # 02 Y:2010 | 02 | 2010 | USE PHOTOCELL CONTROLS | $4,307 | $3,738 | Not Implemented |
SF0386 # 03 Y:2010 | 03 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,677 | $1,600 | Not Implemented |
SF0386 # 04 Y:2010 | 04 | 2010 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,507 | $7,500 | Not Implemented |
SF0386 # 05 Y:2010 | 05 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,553 | $40,720 | Not Implemented |
SF0386 # 06 Y:2010 | 06 | 2010 | INSTALL OCCUPANCY SENSORS | $5,315 | $18,821 | Not Implemented |
SF0386 # 07 Y:2010 | 07 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $217 | $461 | Not Implemented |
TT0053 # 01 Y:2010 | 01 | 2010 | ELIMINATE/REDUCE AN OPERATION | $55,600 | $0 | Not Implemented |
TT0053 # 02 Y:2010 | 02 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,700 | $10,500 | Implemented |