Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

825

matching recommendations
Reset
SIC 20 Food and Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0866 # 06 Y:2013 06 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $865 $3,992 Not Implemented
OK0866 # 07 Y:2013 07 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,853 $22,216 Not Implemented
OK0866 # 08 Y:2013 08 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $299 $463 Not Implemented
OK0866 # 09 Y:2013 09 2013 RECOVER WASTE HEAT FROM EQUIPMENT $5,915 $2,598 Not Implemented
OK0866 # 10 Y:2013 10 2013 INCREASE AMOUNT OF CONDENSATE RETURNED $1,019 $700 Not Implemented
OK0866 # 11 Y:2013 11 2013 INSULATE BARE EQUIPMENT $232 $280 Implemented
OK0866 # 12 Y:2013 12 2013 ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS $2,408 $2,686 Not Implemented
OK0866 # 13 Y:2013 13 2013 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $189 $2,098 Not Implemented
OK0866 # 14 Y:2013 14 2013 REDUCE HEAT GAIN BY WINDOW TINTING $1,077 $16,000 Implemented
OK0857 # 01 Y:2013 01 2013 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT $46,232 $492,750 Not Implemented
OK0811 # 01 Y:2011 01 2011 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $127,513 $58,126 Not Implemented
OK0811 # 02 Y:2011 02 2011 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $17,432 $60,934 Not Implemented
OK0811 # 03 Y:2011 03 2011 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $2,854 $2,600 Implemented
OK0811 # 04 Y:2011 04 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,132 $60,156 Not Implemented
OK0811 # 05 Y:2011 05 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,716 $11,429 Not Implemented
OK0811 # 06 Y:2011 06 2011 INSTALL OCCUPANCY SENSORS $160 $944 Implemented
OK0811 # 07 Y:2011 07 2011 RECOVER WASTE HEAT FROM EQUIPMENT $32,372 $270,346 Not Implemented
OK0811 # 08 Y:2011 08 2011 MINIMIZE WATER USAGE $159,930 $46,397 Not Implemented
OK0811 # 09 Y:2011 09 2011 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $61,620 $459 Not Implemented
OK0811 # 10 Y:2011 10 2011 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $22,682 $0 Implemented
OK0804 # 01 Y:2011 01 2011 Install Anaerobic Digester $544,130 $5,652,880 Not Implemented
OK0804 # 02 Y:2011 02 2011 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $64,961 $238,050 Not Implemented
OK0804 # 03 Y:2011 03 2011 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS $12,835 $19,625 Not Implemented
OK0804 # 04 Y:2011 04 2011 INSTALL SET-BACK TIMERS $740 $1,625 Not Implemented
OK0804 # 05 Y:2011 05 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,796 $56,474 Implemented