Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21,186
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0633 # 06 Y:2025 | 06 | 2025 | INSULATE BARE EQUIPMENT | $3,235 | $4,152 | n/a |
SF0633 # 07 Y:2025 | 07 | 2025 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $10,943 | $20,376 | n/a |
SF0633 # 08 Y:2025 | 08 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $32,940 | $114,566 | n/a |
SF0633 # 09 Y:2025 | 09 | 2025 | MINIMIZE WATER USAGE | $3,105 | $23,556 | n/a |
SF0633 # 10 Y:2025 | 10 | 2025 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $8,335 | $80,990 | n/a |
SF0633 # 11 Y:2025 | 11 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $223,918 | $872,791 | n/a |
UW2501 # 01 Y:2025 | 01 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $41,957 | $25,000 | n/a |
UW2501 # 02 Y:2025 | 02 | 2025 | REPAIR OR REPLACE STEAM TRAPS | $83,082 | $9,800 | n/a |
UW2501 # 03 Y:2025 | 03 | 2025 | INSTALL OCCUPANCY SENSORS | $8,699 | $6,545 | n/a |
UW2501 # 04 Y:2025 | 04 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,175 | $10,269 | n/a |
UW2501 # 05 Y:2025 | 05 | 2025 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $6,682 | $32,756 | n/a |
IP0207 # 01 Y:2025 | 01 | 2025 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $7,560 | $0 | n/a |
IP0207 # 02 Y:2025 | 02 | 2025 | OPTIMIZE PLANT POWER FACTOR | $7,162 | $5,708 | n/a |
IP0207 # 03 Y:2025 | 03 | 2025 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $184 | $227 | n/a |
IP0207 # 04 Y:2025 | 04 | 2025 | INSTALL OCCUPANCY SENSORS | $970 | $1,387 | n/a |
IP0207 # 05 Y:2025 | 05 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,969 | $3,653 | n/a |
AS0601 # 01 Y:2025 | 01 | 2025 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $130,000 | $66,000 | n/a |
AS0601 # 02 Y:2025 | 02 | 2025 | RECOVER AND REUSE WASTE MATERIAL | $76,561 | $120,000 | n/a |
AS0601 # 03 Y:2025 | 03 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $21,962 | $176,288 | n/a |
AS0601 # 04 Y:2025 | 04 | 2025 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $4,347 | $618 | n/a |
AS0601 # 05 Y:2025 | 05 | 2025 | INSULATE BARE EQUIPMENT | $852 | $3,546 | n/a |
AS0601 # 06 Y:2025 | 06 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $416 | $942 | n/a |
AS0601 # 07 Y:2025 | 07 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $105 | $180 | n/a |
DL0252 # 01 Y:2025 | 01 | 2025 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $2,602 | $0 | n/a |
DL0252 # 02 Y:2025 | 02 | 2025 | REDUCE VENTILATION AIR | $4,684 | $1,500 | n/a |